TILE AND STONE · INTERIORS AND FINISHES · FIXED BY STEP 01

The Dye Lot Forces You To Buy The Whole Job Up Front

One purchase order has to cover the entire floor, and it gets placed before the GC has a slab. On a $180K scope that's $70-90K out the door months ahead of any pay application.

WHY IT'S A TILE AND STONE PROBLEM

A plumber buys fixtures in phases and nothing about the third order looks different from the first, so he can pace his buying against his cash. Tile has no phase option, because the material is the job's appearance, so the buy is all at once and it happens months ahead of installation. Natural stone tightens it further: a slab bundle comes off a single block, the vein match dies with that block, and a distributor holds the bundle only 7-30 days without a deposit of roughly 50%.

WHAT IT COSTS

The size of it

On a $180K commercial tile scope, $70-90K of material and deposits leaves the account 3-5 months before the first pay application can bring any of it back, plus warehousing or demurrage while the container waits on a building that isn't ready to receive it. If the run sells out and you underbought, the makeup order is a different shade and the fix is replacing the whole field, not the shortfall.

OVERHEAD AT $1M–$5M
14%
CFOS target 13% for tile and stone.
GROSS MARGIN AT $1M–$5M
22%
CFOS target 24.5% for tile and stone.
NET PROFIT AT $1M–$5M
8%
CFOS target 11.5% for tile and stone.

Ceramic and porcelain come out of the kiln in dye lots, and every run has its own shade and its own caliber stamp for size. Two runs of the same SKU can be visibly different in color and off by 1-2mm in size, so a second order later in the job will never blend into the first. That means one purchase order for 100% of the field tile, plus 10-15% cut waste and whatever attic stock the owner wants, all from one run, before anybody sets a square foot. Imported porcelain out of Italy, Spain, or Turkey runs 8-16 weeks order to delivery, and matching trim or bullnose often runs longer because trim comes off a separate production line.

WHAT TO DO

Three moves, in order

STEP 01
Pull your last three tile purchase orders and write the date the money left the bank next to the date the pay application covering that material got funded. Those days in between are your material float, and they belong in the job's cash plan before you sign the next contract.
STEP 02
Code deposits, freight, duty, and storage to the job's material cost code instead of letting them go to overhead, so each job absorbs the cash it caused.
STEP 03
Ask for a stored materials line and a deposit-triggered draw in the subcontract at buyout, and attach the mill's written lead time as the reason you need it.
QUESTIONS

What tile and stone owners ask

How do I get paid for tile I had to buy months before the job started?

One purchase order has to cover the entire floor, and it gets placed before the GC has a slab. On a $180K scope that's $70-90K out the door months ahead of any pay application.

What does it cost?

On a $180K commercial tile scope, $70-90K of material and deposits leaves the account 3-5 months before the first pay application can bring any of it back, plus warehousing or demurrage while the container waits on a building that isn't ready to receive it. If the run sells out and you underbought, the makeup order is a different shade and the fix is replacing the whole field, not the shortfall.

What do I do first?

Pull your last three tile purchase orders and write the date the money left the bank next to the date the pay application covering that material got funded. Those days in between are your material float, and they belong in the job's cash plan before you sign the next contract.

What are tile and stone contractors supposed to be making?

Tile and stone runs 22% gross margin, 14% overhead and 8% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade is 1 point above it. The CFOS target is 11.5%.

Which part of the system fixes it?

The step is number 01, job cost structure. Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words. It comes from chapter 1 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for tile and stone contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, run by the same author.

What a fractional CFO does for tile and stone contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.