TILE AND STONE · INTERIORS AND FINISHES · FIXED BY STEP 04

Ten Guys Can't Beat A 24 Hour Cure

The GC compressed the schedule and wants more men on the floor, but the floor is set and waiting on grout. The restroom scope you bid as one trip has turned into four.

WHY IT'S A TILE AND STONE PROBLEM

Every other trade recovers schedule with bodies. A framer doubles the crew and the wall goes up twice as fast; tile goes at the speed of chemistry whether one man or ten is on the slab. So tile is the trade that can't answer a compressed schedule with manpower, and it's also the trade whose scope gets fractured into separate trips by the sequence of everybody else's work.

WHAT IT COSTS

The size of it

Three or four mobilizations on a $12K restroom scope wipe out the labor margin before the first tile gets set. When the GC compresses the schedule, you either pay overtime you never priced or you take the delay backcharge.

OVERHEAD AT $1M to $5M
14%
CFOS target 13% for tile and stone.
GROSS MARGIN AT $1M to $5M
22%
CFOS target 24.5% for tile and stone.
NET PROFIT AT $1M to $5M
8%
CFOS target 11.5% for tile and stone.

Thinset needs 24-48 hours before grout, grout needs 24-72 hours before traffic, and a shower waterproofing assembly needs a 24-48 hour flood test that has to pass before anything covers it, all of it with 50 degrees held through cure. Putting a second crew on a floor that's already set moves none of those clocks. The scope also comes in pieces: restroom floors and wainscot before partitions and accessories, base at the toilet partitions on a second trip, the lobby whenever the GC releases it, and punch as a fourth. Every one of those trips is a truck, a mixer, a saw setup, water, and half a day of travel no one paid for.

WHAT TO DO

Three moves, in order

STEP 01
Count the real trips on your last five jobs off truck tickets and crew hours, then set that against the number of mobilizations you priced in the estimate.
STEP 02
Price mobilizations as a separate line with a stated quantity, and put a fixed dollar amount per trip in the proposal for anything beyond that count.
STEP 03
Give the GC your cure and flood test durations in writing at the preconstruction meeting so the schedule shows the days the material owns, not just the days your crew is on site.
QUESTIONS

What tile and stone owners ask

How do I charge a GC for extra mobilizations on a tile job?

The GC compressed the schedule and wants more men on the floor, but the floor is set and waiting on grout. The restroom scope you bid as one trip has turned into four.

What does it cost?

Three or four mobilizations on a $12K restroom scope wipe out the labor margin before the first tile gets set. When the GC compresses the schedule, you either pay overtime you never priced or you take the delay backcharge.

What do I do first?

Count the real trips on your last five jobs off truck tickets and crew hours, then set that against the number of mobilizations you priced in the estimate.

What are tile and stone contractors supposed to be making?

Tile and stone has 22% gross margin, 14% overhead and 8% net profit after taxes at $1M to $5M. The all-trade average is 7%, so this trade is 1 point above it. The CFOS target is 11.5%.

Which part of the system fixes it?

The step is number 04, estimating system. The estimate maps one to one onto the job cost codes, so variance means something the day it appears. It comes from chapter 4 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for tile and stone contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for tile and stone contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.