CFOS for QuickBooks, coming January 2027See what you get
PROOFTENANT IMPROVE
TENANT IMPROVEMENT GENERAL CONTRACTOR · $5M TO $10M

6.7% to 11.2% net profit in 120 days

A tenant improvement GC was using each new job to finish the last one, and could see two weeks ahead at best.

NET PROFIT
6.7% to 11.2%
WORTH PER YEAR
about $225,000
OVERHEAD REMOVED
4 points, about $200,000/yr
CORRECT OVERHEAD RATE CALCULATED
16.4%, had been bid at 10%
MERCHANT CASH ADVANCES RETIRED
two, about $389,000/yr
ADDITIONAL DEBT PAID DOWN
$38,000
WHERE IT STARTED

What it looked like from the owner's chair

Revenue had moved between $3M and $8M with $9M projected, and cash was reactive the whole way. He had debt from a bad year and was working on a two week visibility window, so a job trending tight announced itself when it happened, not 60 days out. In his own words he was using income from new projects to finish and close projects already underway, and he couldn't see how to get off it.

THE CAUSE

What was actually happening

THE MECHANISM

Four things added up. The estimates missed costs, so markup became a contingency for scope no one priced. Overhead went into bids at 10%. The business had operated at 16.4% the previous quarter. Tenant improvement work is feast and famine, and the bid rate never moved with it. There was no job costing, so no report showed that project manager and superintendent time was charged at about half what it cost. Collections were slow on top of all that. Every job was underpriced before a crew mobilized, and the next job had to cover the shortfall.

This is a known failure and it has a page of its own, with what it costs and how to size it in your business.

WHAT WE CHANGED

The work

We rebuilt the estimating template to price the work honestly: 10% of all labor for superintendent nonproductive time, 10% of superintendent time for project manager support, 10% for assistant project manager support, and a financing line for funding material and subcontractors 30 days ahead of getting paid for them. Then weekly cash flow forecasting, which is what gave him enough runway to see work slowing and trim overhead ahead of it rather than after. That took 4 points out of the overhead rate, about $200,000 a year at his volume.

WHAT HAPPENED

The result

Net profit went from 6.7% to 11.2% inside 120 days, a 4.5 point swing worth roughly $225,000 a year. Two merchant cash advances were retired, one at $4,200 a week and one at $14,200 a month, about $389,000 a year of debt service that stopped leaving the business, plus another $38,000 of debt paid down. Most of that gain is the overhead cut. The rebuilt estimating template hadn't fully worked through at the 120 day mark because jobs bid under the old pricing were still moving through backlog, so there's more coming.

QUESTIONS

What owners ask about this one

What was actually wrong?

Four things added up. The estimates missed costs, so markup became a contingency for scope no one priced. Overhead went into bids at 10%. The business had operated at 16.4% the previous quarter. Tenant improvement work is feast and famine, and the bid rate never moved with it. There was no job costing, so no report showed that project manager and superintendent time was charged at about half what it cost. Collections were slow on top of all that. Every job was underpriced before a crew mobilized, and the next job had to cover the shortfall.

What did you change?

We rebuilt the estimating template to price the work honestly: 10% of all labor for superintendent nonproductive time, 10% of superintendent time for project manager support, 10% for assistant project manager support, and a financing line for funding material and subcontractors 30 days ahead of getting paid for them. Then weekly cash flow forecasting, which is what gave him enough runway to see work slowing and trim overhead ahead of it rather than after. That took 4 points out of the overhead rate, about $200,000 a year at his volume.

How long did it take?

120 days. That is the time to the result on this page. It does not count the last piece of the install.

Which part of the system did it?

step 03, overhead calculation, step 04, estimating system and step 07, monthly cadence. Installed in dependency order, which is the same order every client gets, because a step that reads from a number the one before it never established produces output that looks finished and isn't.

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.