CFOS for QuickBooks, coming January 2027See what you get
CONCRETECFOS-01
CONCRETE · CONCRETE AND MASONRY · FIXED BY STEP 01

Six Trips Back for Pads and Sidewalks, One Unit Price

You were first on the site and you're still coming back for stairs, pads, curbs, and exterior flatwork, all priced inside a per-yard number that assumed you never left.

WHY IT'S A CONCRETE PROBLEM

You're first on and nearly last off, and no other trade has that spot in the schedule. Your small-quantity work is spread across a year of somebody else's sequence. The unit price you bid assumed continuous placement rates, so every return trip is priced as part of the big pour. These trips never get bid as separate mobilizations, so the cost has no line in the estimate and no cost code in the field.

WHAT IT COSTS

The size of it

The last 5 percent of contract value routinely takes 15 to 20 percent of the job's labor hours, at the worst production rates on the job. It happens after you've reported the job substantially complete and profitable. The loss only turns up in the final job report, and by then it has repeated across the whole portfolio.

OVERHEAD AT $1M to $5M
14%
CFOS target 13% for concrete.
GROSS MARGIN AT $1M to $5M
21%
CFOS target 23.5% for concrete.
NET PROFIT AT $1M to $5M
7%
CFOS target 10.5% for concrete.

Concrete takes six mobilizations, and the last five are all small quantities. Footings, walls, and slab-on-grade are continuous production with good rates and a full crew. Then the crew returns for a stair flight, a couple of housekeeping pads, a curb line, and the exterior flatwork, each trip needing a crew, trucking, sometimes a pump, and a load small enough to draw a short-load fee below roughly 4 yards. Winter returns add ACI 306 protection on top, which means blankets, heat, and accelerator that were never in the estimate.

WHAT TO DO

Three moves, in order

STEP 01
Create a numbered remobilization cost code for each return trip. Make the foreman code hours and trucking to the trip number.
STEP 02
Take your three biggest jobs from last year and total every hour charged after the final structural placement, then compare that to the revenue those trips produced.
STEP 03
On the next bid, itemize stairs, pads, curbs, and exterior flatwork as their own line items with a stated minimum load, a mobilization charge, and cold-weather protection priced separately.
QUESTIONS

What concrete owners ask

How to bid concrete remobilization for pads and sidewalks?

You were first on the site and you're still coming back for stairs, pads, curbs, and exterior flatwork, all priced inside a per-yard number that assumed you never left.

What does it cost?

The last 5 percent of contract value routinely takes 15 to 20 percent of the job's labor hours, at the worst production rates on the job. It happens after you've reported the job substantially complete and profitable. The loss only turns up in the final job report, and by then it has repeated across the whole portfolio.

What do I do first?

Create a numbered remobilization cost code for each return trip. Make the foreman code hours and trucking to the trip number.

What are concrete contractors supposed to be making?

Concrete has 21% gross margin, 14% overhead and 7% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.

Which part of the system fixes it?

The step is number 01, job cost structure. Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words. It comes from chapter 1 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for concrete contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for concrete contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.