CFOS for QuickBooks, coming January 2027See what you get
CONCRETECFOS-06
CONCRETE · CONCRETE AND MASONRY · FIXED BY STEP 06

The 28-Day Break Decides a Pour You Already Billed

You poured in March on an approved mix, the cylinders came back low in April, and two floors have already gone up on the slab in question.

WHY IT'S A CONCRETE PROBLEM

Almost every other trade gets inspected while its work is still exposed and cheap to fix. Concrete gets a verdict four weeks later, on work other trades have already built on top of. So the remedy is tearing out somebody else's progress before you tear out yours. The mix approval clock on the front end works the same way. It puts dead time on a mobilized crew while a lab and an engineer decide when you can batch, and your payroll puts no pressure on them.

WHAT IT COSTS

The size of it

Coring, load testing, and remedial work are unbudgeted direct costs. They post to the current period against a job phase you closed a month earlier. Until the dispute settles, the GC withholds against the entire pay application, including the pours no one disputes.

OVERHEAD AT $1M to $5M
14%
CFOS target 13% for concrete.
GROSS MARGIN AT $1M to $5M
21%
CFOS target 23.5% for concrete.
NET PROFIT AT $1M to $5M
7%
CFOS target 10.5% for concrete.

There are two clocks on every placement and you own neither one. Before the first truck, the mix design goes to the engineer of record and the testing lab with historical strength data for review, and until it comes back approved you can't batch a yard. After the pour, acceptance works backward: cylinders break at 28 days, and a low break triggers core drilling, load testing, engineering evaluation, or removal. By then the slab is covered by subsequent work and the pay application it was billed on has already been approved.

WHAT TO DO

Three moves, in order

STEP 01
Keep the pour phase open in job cost until the 28-day break comes back, so late charges post to the placement that caused them.
STEP 02
Treat mix design submittal and approval as a scheduled milestone with one person responsible and a due date, then log the days between submittal and approval on every job.
STEP 03
Log every break result against its placement date, truck tickets, and batch plant, so a low break tells you which yards are in question within the hour.
QUESTIONS

What concrete owners ask

Failed cylinder break at 28 days who pays for coring?

You poured in March on an approved mix, the cylinders came back low in April, and two floors have already gone up on the slab in question.

What does it cost?

Coring, load testing, and remedial work are unbudgeted direct costs. They post to the current period against a job phase you closed a month earlier. Until the dispute settles, the GC withholds against the entire pay application, including the pours no one disputes.

What do I do first?

Keep the pour phase open in job cost until the 28-day break comes back, so late charges post to the placement that caused them.

What are concrete contractors supposed to be making?

Concrete has 21% gross margin, 14% overhead and 7% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.

Which part of the system fixes it?

The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It comes from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for concrete contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for concrete contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.