CONCRETE · CONCRETE AND MASONRY · FIXED BY STEP 07

Done in June, Retention Releases When the Building Opens

Footings, foundations, and slab-on-grade are the first real dollar volume on the site, so you bill most of your contract early and then wait on a building you left a year and a half ago.

WHY IT'S A CONCRETE PROBLEM

Trades that finish near the end of the build wait weeks for retention, because their substantial completion and the project's are close together. You finish first and wait the full length of the building, which means the concrete contractor is the one financing everybody else's schedule. Multiply that across four or five concurrent jobs and the retention receivable becomes the largest asset you own, with nothing in your reporting flagging it as such.

WHAT IT COSTS

The size of it

Retention on a concrete package routinely exceeds the profit on that package, so the job that looked done in June is still an unfunded loan in 2027. Most contractors keep it inside ordinary AR, unaged and untracked, which means the single biggest number on the balance sheet goes unchased.

OVERHEAD AT $1M–$5M
14%
CFOS target 13% for concrete.
GROSS MARGIN AT $1M–$5M
21%
CFOS target 23.5% for concrete.
NET PROFIT AT $1M–$5M
7%
CFOS target 10.5% for concrete.

A structural concrete package can be 60 to 70 percent billed by month 4 to 6 of an 18 to 24 month project, then it goes almost silent. Retention of 5 to 10 percent releases at substantial completion of the whole project, not of your scope, and then another 30 to 90 days pass while the GC receives funds and passes them down. Money you earned in month two comes back in month twenty-four. On a $100,000 job at 10 percent retention that's $10,000 held out there, which on most concrete packages is more than the job's entire profit.

WHAT TO DO

Three moves, in order

STEP 01
Split retention out of accounts receivable into its own account and age it by project substantial completion date, not by invoice date.
STEP 02
Build a one-page retention log listing every closed job, the withheld amount, the GC contact, and the release trigger, then work it in the monthly meeting like a punch list.
STEP 03
Price the cost of waiting at bid: know what holding 10 percent for twenty months costs you at your line of credit rate, and put that number into the price you give the GC.
QUESTIONS

What concrete owners ask

Retention still held two years after we finished the slab?

Footings, foundations, and slab-on-grade are the first real dollar volume on the site, so you bill most of your contract early and then wait on a building you left a year and a half ago.

What does it cost?

Retention on a concrete package routinely exceeds the profit on that package, so the job that looked done in June is still an unfunded loan in 2027. Most contractors keep it inside ordinary AR, unaged and untracked, which means the single biggest number on the balance sheet goes unchased.

What do I do first?

Split retention out of accounts receivable into its own account and age it by project substantial completion date, not by invoice date.

What are concrete contractors supposed to be making?

Concrete runs 21% gross margin, 14% overhead and 7% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.

Which part of the system fixes it?

The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: The Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, andCONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for concrete contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, run by the same author.

What a fractional CFO does for concrete contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.