ELECTRICAL · ELECTRICAL AND TECHNOLOGY · FIXED BY STEP 07

Retainage on gear is a loan you didn't agree to

Gear billed as stored material gets retainage at the same rate as labor, even though you funded 100 percent of it in cash before billing a dollar.

WHY IT IS A ELECTRICAL PROBLEM

Electrical carries a far higher equipment to labor ratio on the front half of a job than the trades it shares a wall with, so retainage on material is a much larger line here than anywhere else on the GC's subcontractor list. Retainage held against labor at least trails a payroll you funded 30 to 45 days earlier. The same percentage held against gear trails a wire transfer you made a year earlier, for an asset the owner already holds title to.

WHAT IT COSTS

The size of it

On $500k of gear at 10 percent, $50k of cash you already spent sits with the GC for 18 to 24 months. Retention receivable on a $5M electrical shop typically runs $250k to $400k, which is the entire line of credit, borrowed at 9 to 11 percent to carry money you already earned.

OVERHEAD AT $1M–$5M
16%
CFOS target 15% for electrical.
GROSS MARGIN AT $1M–$5M
25%
CFOS target 26% for electrical.
NET PROFIT AT $1M–$5M
9%
CFOS target 11% for electrical.

Retainage exists to protect the owner against defective work and incomplete performance, and a piece of gear you bought, insured, and delivered is neither. Carve material and equipment out of the retainage basis in the subcontract, because that argument is easy to make at signing and impossible to make later. The math runs one way: cash left your account at 100 percent on a wire to the supplier, and it comes back at 90 or 95 cents on a release schedule someone else controls. On a job where equipment is most of the front half billing, the distance between those two numbers is bigger than most electricians ever write down.

WHAT TO DO

Three moves, in order

STEP 01
Pull your three largest active subcontracts, find the retainage clause, and mark whether it reaches stored material and equipment or stops at labor and installed work.
STEP 02
On the next contract, ask for equipment to be excluded from the retainage basis, or for retainage on material to release at delivery and acceptance rather than at final completion.
STEP 03
Split the schedule of values so gear sits on its own line with its own retainage treatment, and report retention receivable by job and by GC every month.
QUESTIONS

What electrical owners ask

Can a general contractor hold retainage on stored materials I already paid for?

Gear billed as stored material gets retainage at the same rate as labor, even though you funded 100 percent of it in cash before billing a dollar.

What does it cost?

On $500k of gear at 10 percent, $50k of cash you already spent sits with the GC for 18 to 24 months. Retention receivable on a $5M electrical shop typically runs $250k to $400k, which is the entire line of credit, borrowed at 9 to 11 percent to carry money you already earned.

What do I do first?

Pull your three largest active subcontracts, find the retainage clause, and mark whether it reaches stored material and equipment or stops at labor and installed work.

What are electrical contractors supposed to be making?

Electrical runs 25% gross margin, 16% overhead and 9% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 2 points above it. The CFOS target is 11%.

Which part of the system fixes it?

The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: The Construction Financial Operating System.

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Josh Luebker ran commercial construction projects before he ran the numbers behind them, on data centres, military bases, hospitals, and high-rises. He wrote CONTROL: The Construction Financial Operating System, which is an eight-step framework for commercial subcontractors, and it publishes on October 1, 2026. He is a master electrician who moved into the office and kept the field vocabulary.

Sulphur Prairie Operations LLC maintains the benchmark reference behind these figures. Every edition is reconciled against the newest CFMA survey release before it publishes here. Where a figure changes between editions, the older edition keeps its year in the title so a citation to it stays correct.

Eight steps. Sixty days.

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It publishes on October 1, 2026. Eight steps, six working templates, and the order they install in.