Your gear release clock starts at the power company
Gear can't release for fabrication until the utility publishes available fault current, and the utility isn't on your subcontract at all.
No other trade's fabrication release depends on a letter from a regulated monopoly that has no contract with anyone on the site. The study sets protective device settings and arc flash labeling, which makes the utility letter a hard gate in front of a 30 to 60 week build rather than a paperwork step. Everyone on the job treats energization as the electrician's date, and the electrician controls none of the three parties who set it.
The size of it
Six to ten weeks of pre release delay pushes energization by the same six to ten weeks, and you absorb an extra winter of general conditions, supervision, and a remobilization nobody priced. On a $1.2M electrical scope that's $40k to $90k of field overhead that never reads as a variance, because there's no cost code for waiting.
Ask for the available fault current letter the week the service size is set, not the week the submittal is due. The chain runs one direction: utility fault current letter, then the PE stamped short circuit, coordination, and arc flash study, then the gear submittal, then approval, then release to fabrication, then a 30 to 60 week build. A study house won't stamp against an assumed fault current, because the breaker settings and the incident energy labels on the doors depend on the real number. Every week burned at the front of that chain moves to the back of the longest lead item on the job, so a six week wait for one letter is a six week push on energization.
Three moves, in order
Step 06: Project management
Billing dates, change orders, and notices, run as standards that hold without anyone chasing them.
What else costs electrical contractors money
The same mechanism in other trades
What electrical owners ask
Short circuit study waiting on the utility is holding up my gear release?
Gear can't release for fabrication until the utility publishes available fault current, and the utility isn't on your subcontract at all.
What does it cost?
Six to ten weeks of pre release delay pushes energization by the same six to ten weeks, and you absorb an extra winter of general conditions, supervision, and a remobilization nobody priced. On a $1.2M electrical scope that's $40k to $90k of field overhead that never reads as a variance, because there's no cost code for waiting.
What do I do first?
File the utility service application and the written request for available fault current the same week the service size is set, and put that request date on the schedule as its own milestone.
What are electrical contractors supposed to be making?
Electrical runs 25% gross margin, 16% overhead and 9% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 2 points above it. The CFOS target is 11%.
Which part of the system fixes it?
The step is number 06, project management. Billing dates, change orders, and notices, run as standards that hold without anyone chasing them. It comes from chapter 6 of CONTROL: The Construction Financial Operating System.
