CONCRETE AND MASONRY · TRADE BENCHMARKS

Where concrete contractors lose money

6 things cost concrete contractors money without ever showing up as a line item, and each one traces to a step you can install. Concrete contractors average 21% gross margin, 14% overhead and 7% net profit at $1M–$5M of revenue. The CFOS target at that size is 23% gross margin, 13% overhead and 10% net, and the gap of 3 points on the bottom line is where those mechanisms live. Figures for all 7 revenue bands are in the table below.

Concrete sits 2nd of 5 in concrete and masonry on net profit, and it carries leaner overhead than the 48-trade average. Here is every figure, across all 7 revenue bands.

OVERHEAD AT $1M–$5M
14%
CFOS target 13%. Shares this figure with 10 other trades, and sits 0.6 points below the concrete and masonry average.
GROSS MARGIN AT $1M–$5M
21%
CFOS target 23%. Shares this figure with 5 other trades, and sits 0.8 points below the concrete and masonry average.
NET PROFIT AT $1M–$5M
7%
CFOS target 10%. Shares this figure with 16 other trades, and sits 0.2 points below the concrete and masonry average.
ACROSS EVERY BAND

Concrete by revenue band

CONCRETE · SPM TRADE BENCHMARK REFERENCE
Metric$1M–$5M$5M–$10M$10M–$25M$25M–$50M$50M–$100M$100M–$500M$500M+CFOS target
Overhead14%13%12%11%10%9%8%13%
Gross margin21%22%23%24%25%26%28%23%
Net profit7%9%11%13%15%17%20%10%
CITE THIS

SPM The Construction CFO. SPM Trade Benchmark Reference: Concrete. 2026. Sulphur Prairie Management, LLC. https://runoncfos.com/trades/concrete. CC BY 4.0.

Figures on this page were last revised 2026-08-21. Published under CC BY 4.0, which permits reuse of any figure here, including commercially, as long as the credit above travels with it. The same figures in machine-readable form: /benchmarks.json.

Trade level gross margin and overhead compiled by SPM The Construction CFO, validated against published CFMA and JMCO benchmarks. The CFOS targets beside them are from the book CONTROL: The Construction Financial Operating System, published with the full reference at runoncfos.com.

SOURCES
  1. 2024 Construction Financial Benchmarker, Executive Summary, Construction Financial Management Association, 2024.
  2. 2025 Performance Benchmarks, Construction Companies, Jones Maresca and Company, 2025.
  3. SPM Trade Benchmark Reference, Sulphur Prairie Management, LLC, 2026.

Sourcing and method: the methodology page.

Which bands are measured. The 4 bands above $10M–$25M carry the survey curve further out and have not been reconciled against the licensed CFMA Benchmarker. How every figure was built is set out on the methodology page.

WHAT GOES WRONG IN THIS TRADE

6 problems specific to concrete

WHAT GOES WRONG HERE

The EOR approved the placing drawings, the fab shop cut and bent to the bar list, and then somebody moved a footing. You poured in March on an approved mix, the cylinders broke low in April, and two floors are already sitting on the slab in question. Your yard is full of panels and shoring, every job report says you made money, and the bank account disagrees. Concrete has about a 90-minute working life from batch to placement, so your supply market is a haul radius with two or three plants.

Each one below points at the item, the unit, the clock, or the party that makes it a concrete problem, and it says which step fixes it.

CONCRETE · WHY EACH ONE IS A CONCRETE PROBLEM
MechanismWhy it's specific to this tradeStep
Eight Tons of Rebar Tagged to a Drawing That ChangedStructural steel can be re-detailed and re-sequenced into another package because it's still a member that bolts to something else. A bent #8 can't be un-bent, and no other job in your backlog has that bend schedule, so there's no salvage path and no transfer. You're also carrying the delay twice, because the replacement release has to go back through detailing, approval, and the fab shop queue before a single truck moves.Project management
The 28-Day Break Decides a Pour You Already BilledAlmost every other trade gets inspected while its work is still exposed and still cheap to fix. Concrete gets a verdict four weeks after the fact, on work that other trades have already built on top of, which means the remedy is demolition of somebody else's progress before it's demolition of yours. The mix approval clock on the front end works the same way, since it puts dead time on a mobilized crew while a lab and an engineer who feel no pressure from your payroll decide when you can batch.Project management
Ten Jobs Used Those Forms, One Job Paid for ThemRental accrues on calendar days while forms only earn on pour cycles, so the two clocks run at different speeds and only one of them is under your control. A trade that buys tools and consumables can spread cost by the hour or the piece. You're spreading a large capital item across pour cycles that a lab technician releases, which is why the same panel set can be cheap on one job and expensive on the next with nothing about the panels having changed.Equipment cost basis
Your Ready-Mix Quote Expired Eleven Months Before the PourA contractor buying wire, pipe, or lumber can lock a price, take delivery early, and sit on the material in a warehouse. You can't warehouse concrete for even two hours, so every yard is bought at whatever the price is the morning it pours, from a supplier with no real competition inside the haul radius. That makes escalation a structural exposure on your largest material line, not a bad-luck event.Estimating system
Done in June, Retention Releases When the Building OpensTrades that finish near the end of the build wait weeks for retention, because their substantial completion and the project's are close together. You finish first and wait the full length of the building, which means the concrete contractor is the one financing everybody else's schedule. Multiply that across four or five concurrent jobs and the retention receivable becomes the largest asset you own, with nothing in your reporting flagging it as such.Monthly cadence
Six Trips Back for Pads and Sidewalks, One Unit PriceBeing first on and nearly last off is a scheduling position no other trade holds, and it means your small-quantity work is spread across a year of somebody else's sequence. The unit price you bid was built on continuous placement rates, so every return trip is priced as though it were part of the big pour. Nobody bids these as separate mobilizations, so the cost has no home in the estimate and no cost code in the field.Job cost structure
HOW IT COMPARES

Concrete against the other 47 trades

CONCRETE · RANK AND SPREAD AT $1M–$5M
MetricConcreteConcrete and masonry averageAll 48 averageRank
Overhead14%14.6%15.1%6th of 48
Gross margin21%21.8%22.1%33rd of 48
Net profit7%7.2%7%21st of 48
WHAT THE RANKING SAYS

Concrete sheds 6 points of overhead between $1M–$5M and $500M+, against 6 for concrete and masonry as a group. Inside that group, Concrete flatwork keeps the most at 8%, and Concrete, Concrete flatwork and Masonry all run 14% overhead, the leanest. The leanest one is this trade.

QUESTIONS

What owners ask

What overhead should a concrete contractor run?

Concrete shares its overhead figure with 10 other trades at this revenue, which is what the published data resolves to. It runs 14% at $1M–$5M and 8% at $500M+, as a percentage of revenue. That sits 0.6 points below the concrete and masonry average of 14.6%. The CFOS target at $1M–$5M is 13%. The CFOS target is one point leaner than your trade's average at your revenue.

What gross margin should a concrete contractor run?

Concrete shares its gross margin figure with 5 other trades at this revenue, which is what the published data resolves to. It runs 21% at $1M–$5M and 28% at $500M+, as a percentage of revenue. That sits 0.8 points below the concrete and masonry average of 21.8%. The CFOS target at $1M–$5M is 23%. The CFOS target is published at $1M to $5M. It's set at whatever gross margin produces the net profit target once overhead is paid, and never below your trade's own average.

What net profit should a concrete contractor run?

Concrete shares its net profit figure with 16 other trades at this revenue, which is what the published data resolves to. It runs 7% at $1M–$5M and 20% at $500M+, before taxes, as a percentage of revenue. That sits 0.2 points below the concrete and masonry average of 7.2%. The CFOS target at $1M–$5M is 10%. The CFOS target is published at $1M to $5M.

What profit margin should a small concrete business run?

Owners usually mean net profit when they say profit margin, and for concrete at $1M–$5M that's 7%. Gross margin is a different number, 21%, and it's what's left after job costs but before overhead. Overhead is the 14% sitting between the two. A small concrete business holding 7% net is at the published figure for its size, and the CFOS target at that revenue is 10%.

Does concrete get more profitable as it grows?

Overhead is the number that moves. Concrete sheds 6 points between $1M–$5M and $500M+, which is in line with the 6 points concrete and masonry sheds as a group. Net profit starts 0 points under the 48-trade average, so the room is in the overhead line before it's anywhere else.

Where does concrete sit against the other trades?

Concrete ties 3 trades in concrete and masonry on net profit, all at 7%. Concrete flatwork keeps the most at 8%. Its overhead is the leanest too, level with Concrete flatwork and Masonry. Gross margin ranks 33rd of 48 and overhead ranks 6th.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, andCONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for concrete contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, run by the same author.

What a fractional CFO does for concrete contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system these figures sit inside. More about the author.

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It publishes on October 1, 2026. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.