INTERIORS · INTERIORS AND FINISHES · FIXED BY STEP 01

Your Door Hardware Stays in a Crate for Nine Months

You cut the deposit on doors, frames, and hardware in the spring so hollow metal frames can go in before the walls close, and the leaves and closers stay crated until finishes.

WHY IT'S AN INTERIORS PROBLEM

A framing sub buys studs and track, then installs them the week the truck unloads. Interiors has to buy finish hardware at framing time, because the frame and the leaf come off the same made-to-order submittal against an approved hardware and keying schedule with fire labels. That makes the package non-returnable and non-substitutable. Electrified sets routinely take 20 to 30 weeks, so you can't split the buy to match the two install dates.

WHAT IT COSTS

The size of it

On a $900K interiors contract the DFH package commonly costs $120K to $180K, and the money goes out long before it comes back in. You fund the single largest material buy in the contract for six to nine months on terms that came due back at frames.

OVERHEAD AT $1M to $5M
13%
CFOS target 12% for interiors.
GROSS MARGIN AT $1M to $5M
19%
CFOS target 22% for interiors.
NET PROFIT AT $1M to $5M
6%
CFOS target 10% for interiors.

The DFH package gets released early because hollow metal frames have to be set before either side of the wall goes on. Frames are the cheap part of that order. Money is in the leaves, closers, exit devices, electrified hardware, and access control prep, and none of that installs until finishes. You end up with one purchase order, one deposit, one supplier net-30 clock, and two install dates six to nine months apart.

WHAT TO DO

Three moves, in order

STEP 01
Split the DFH package across two cost codes on the day you issue the PO, putting frames, anchors, and prep on the framing phase and leaves, closers, and electrified sets on the finish phase.
STEP 02
Ask the supplier for staged billing tied to the two releases, and get a stored materials line into your schedule of values so crated hardware bills while it waits.
STEP 03
Put the hardware submittal approval date and the quoted lead time in front of the GC before the first draw, so the deposit date and the install date are on the same page.
QUESTIONS

What interiors owners ask

Paying for door hardware months before hanging any doors?

You cut the deposit on doors, frames, and hardware in the spring so hollow metal frames can go in before the walls close, and the leaves and closers stay crated until finishes.

What does it cost?

On a $900K interiors contract the DFH package commonly costs $120K to $180K, and the money goes out long before it comes back in. You fund the single largest material buy in the contract for six to nine months on terms that came due back at frames.

What do I do first?

Split the DFH package across two cost codes on the day you issue the PO, putting frames, anchors, and prep on the framing phase and leaves, closers, and electrified sets on the finish phase.

What are interiors contractors supposed to be making?

Interiors has 19% gross margin, 13% overhead and 6% net profit after taxes at $1M to $5M. The all-trade average is 7%, so this trade is 1 point below it. The CFOS target is 10%.

Which part of the system fixes it?

The step is number 01, job cost structure. Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words. It comes from chapter 1 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for interiors contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for interiors contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.