Your disposal outlet is booked before the dig starts
You mobilized, the excavation is open, and the only permitted facility that will take the material is 400 miles away and booked three weeks out.
A framer waiting on material has a stack of lumber doing nothing. A remediation contractor waiting on an outlet has an open excavation with shoring, plates, dewatering, and an air monitoring plan in use every single day, and a permitted facility that answers to its own compliance calendar before it answers to yours. The supply chain here is licensed and short: there's no next yard down the road to call.
The size of it
Haul cost per ton doubles or triples against the local outlet you aren't allowed to use, and every week the facility can't take you is a week of rented shoring, plates, dewatering, and idle iron parked on a hole with nothing billed against it.
On a remediation job the receiving facility sets the schedule and the crew works around it. Hazardous soil can't go to the Subtitle D landfill down the road; it goes to a permitted Subtitle C site, and for most of the country that means one of a few facilities, long haul trucking or rail, and a scheduled tonnage allocation somebody has to reserve. In situ work has the same problem in a different form. Skid mounted SVE, air sparge, and pump and treat systems are built to order on lead times measured in months, and injection reagents like ZVI, persulfate, and EHC get batched per job. None of it waits on a shelf, and the hole is already open while you wait.
Three moves, in order
Step 06: Project management
Billing dates, change orders, and notices, written as standards that work without anyone following up on them.
What else costs environmental remediation contractors money
The same mechanism in other trades
What environmental remediation owners ask
Subtitle c landfill booked out how do I bid disposal?
You mobilized, the excavation is open, and the only permitted facility that will take the material is 400 miles away and booked three weeks out.
What does it cost?
Haul cost per ton doubles or triples against the local outlet you aren't allowed to use, and every week the facility can't take you is a week of rented shoring, plates, dewatering, and idle iron parked on a hole with nothing billed against it.
What do I do first?
Before you price the job, call the two nearest permitted Subtitle C facilities and get their current tonnage allocation and next open window in writing, then put that date in the schedule as a hard constraint.
What are environmental remediation contractors supposed to be making?
Environmental remediation has 23% gross margin, 16% overhead and 7% net profit after taxes at $1M to $5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.
Which part of the system fixes it?
The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It comes from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.
Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for environmental remediation contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.
What a fractional CFO does for environmental remediation contractors