You inherit the slab and pay for the shim labor
The slab is an inch and a half out of square, the concrete crew is gone and paid, and covering it up just became a framing expense.
Every trade after you sets to your lines, so framing is where the design gets forced to match what got poured. Drywall, mechanical, and finish trades get a structure that's already corrected. You get the error itself and have to make it go away. By the time you find it, that correction work has no cost code, change order, or witness on site. No report later shows the day you spent pulling the plate line straight.
The size of it
A crew day per building on a 40-lot subdivision is 40 unbilled crew days, roughly $120K of labor absorbed as "that's just framing." Then it goes into next year's square-foot number, and you can't defend it when the builder pushes back on the increase.
You're the first trade on the structure, so you get whatever the concrete sub left: out-of-square slabs, mis-set anchor bolts, and stemwall elevations that miss the plan. By the time your first plate goes down, that sub has demobilized and been paid, so there's no one left to backcharge. The GC won't open a change order against a sub who's off the schedule, and he won't stop the job to argue about it. So you shim, furr, re-drill for hold-downs, rope the plate line, and absorb the hours, usually a full crew day per building and sometimes more. Those hours post to your cost as ordinary framing labor with no note.
Three moves, in order
Step 04: Estimating system
The estimate maps one to one onto the job cost codes, so variance means something the day it appears.
What else costs framing contractors money
The same mechanism in other trades
What framing owners ask
Can I backcharge for an out of square slab as a framer?
The slab is an inch and a half out of square, the concrete crew is gone and paid, and covering it up just became a framing expense.
What does it cost?
A crew day per building on a 40-lot subdivision is 40 unbilled crew days, roughly $120K of labor absorbed as "that's just framing." Then it goes into next year's square-foot number, and you can't defend it when the builder pushes back on the increase.
What do I do first?
Walk the slab before the first plate goes down: pull diagonals, check anchor bolt locations and stemwall elevations, and photograph what's off with a tape in the frame that same day.
What are framing contractors supposed to be making?
Framing has 18% gross margin, 13% overhead and 5% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 2 points below it. The CFOS target is 10%.
Which part of the system fixes it?
The step is number 04, estimating system. The estimate maps one to one onto the job cost codes, so variance means something the day it appears. It comes from chapter 4 of CONTROL: C.F.O.S. Construction Financial Operating System.
Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for framing contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.