CFOS for QuickBooks, coming January 2027See what you get
FRAMINGCFOS-06
FRAMING · ENVELOPE AND STRUCTURE · FIXED BY STEP 06

Walls stack in four days. Trusses take eight weeks.

The deck is clean, the walls are plumb and braced, and eight guys are on it waiting for a girder truss somebody else was supposed to order.

WHY IT'S A FRAMING PROBLEM

Framing is one of the few trades that gets a structure half built, then stops mid-sequence for a made-to-order component it didn't buy. Trades that install stock material can finish in one mobilization. You stack walls in days, then hold an eight-man crew for a component with a two-month clock.

WHAT IT COSTS

The size of it

An eight-man crew idled or half-used for two weeks is $30K to $50K of payroll against no revenue. Demobilizing to another job and coming back costs two unbilled mobilizations plus a second telehandler delivery you pay for yourself.

OVERHEAD AT $1M to $5M
13%
CFOS target 12% for framing.
GROSS MARGIN AT $1M to $5M
18%
CFOS target 22% for framing.
NET PROFIT AT $1M to $5M
5%
CFOS target 10% for framing.

Girder trusses, hip sets, long-span glulams, LVL and PSL beams, and prefab shear panels are all cut to the job. None of it is on a rack anywhere. Typical truss lead times are 6 to 10 weeks, and more than 16 in a hot market. On a labor-only framing contract the builder buys the package. Nothing tells you when the PO went out, and no one at the fabricator answers to you. Your crew costs the same every week while the fabricator catches up, so the wait comes straight out of your payroll.

WHAT TO DO

Three moves, in order

STEP 01
Ask the builder in writing for the truss PO release date and the fabricator ship date on every start, before you put the crew on the schedule.
STEP 02
Keep a crew calendar showing walls-up dates and truss-set dates as two separate bars, so you see the wait coming before your guys find it on a deck.
STEP 03
Price mobilization and equipment delivery as their own line in the bid, and bill a remobilization every time a deck waits.
QUESTIONS

What framing owners ask

How do I keep my framing crew busy when trusses are delayed?

The deck is clean, the walls are plumb and braced, and eight guys are on it waiting for a girder truss somebody else was supposed to order.

What does it cost?

An eight-man crew idled or half-used for two weeks is $30K to $50K of payroll against no revenue. Demobilizing to another job and coming back costs two unbilled mobilizations plus a second telehandler delivery you pay for yourself.

What do I do first?

Ask the builder in writing for the truss PO release date and the fabricator ship date on every start, before you put the crew on the schedule.

What are framing contractors supposed to be making?

Framing has 18% gross margin, 13% overhead and 5% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 2 points below it. The CFOS target is 10%.

Which part of the system fixes it?

The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It comes from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for framing contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for framing contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.