FRAMING · ENVELOPE AND STRUCTURE · FIXED BY STEP 04

Nothing in your books turns hours back into square feet

You bid the plan by the square foot and pay the crew by the hour or by the unit, and nothing you own converts one into the other.

WHY IT IS A FRAMING PROBLEM

Almost no other trade bids in one unit and buys its biggest cost in a different one. A plumber bids fixtures and buys fixtures; an electrician bids devices and buys devices. Framing bids floor area and pays labor by the clock or by the piece, so the conversion has to be built on purpose or it simply doesn't exist.

WHAT IT COSTS

The size of it

A framer running 12 plans across two builders can carry two or three losing plans for a full season without knowing which ones. On $4M of labor-only volume, a 60-cent-per-square-foot blind spot on a third of the starts is $150K to $250K of margin that never surfaces as one identifiable loss.

OVERHEAD AT $1M–$5M
13%
CFOS target 12% for framing.
GROSS MARGIN AT $1M–$5M
18%
CFOS target 22% for framing.
NET PROFIT AT $1M–$5M
5%
CFOS target 10% for framing.

Your largest cost line is priced in a unit your contract never uses. The contract says $6.40 per square foot of floor area on Plan 2340. Cost comes back as gross payroll plus burden by the week, or as a piece-rate check by unit, and nothing in between turns those dollars into square feet produced. So you can't tell anyone what a Plan 2340 cost you, and when the builder asks for next season's number you give him last year's number, because last year's number is the only one you own.

WHAT TO DO

Three moves, in order

STEP 01
Put the plan number and the floor square footage on every framing job in your cost file, so labor dollars sit against a plan and a square foot count and not just a builder.
STEP 02
Take last week's payroll and piece-rate checks, divide by square feet framed on each plan, and write the real dollars per square foot next to the bid dollars per square foot on one sheet.
STEP 03
Take the three plans with the widest spread and reprice them before you sign the next schedule of values.
QUESTIONS

What framing owners ask

How do i know what a framing plan costs me per square foot?

You bid the plan by the square foot and pay the crew by the hour or by the unit, and nothing you own converts one into the other.

What does it cost?

A framer running 12 plans across two builders can carry two or three losing plans for a full season without knowing which ones. On $4M of labor-only volume, a 60-cent-per-square-foot blind spot on a third of the starts is $150K to $250K of margin that never surfaces as one identifiable loss.

What do I do first?

Put the plan number and the floor square footage on every framing job in your cost file, so labor dollars sit against a plan and a square foot count and not just a builder.

What are framing contractors supposed to be making?

Framing runs 18% gross margin, 13% overhead and 5% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 2 points below it. The CFOS target is 10%.

Which part of the system fixes it?

The step is number 04, estimating system. The estimate maps one to one onto the job cost codes, so variance means something the day it appears. It comes from chapter 4 of CONTROL: The Construction Financial Operating System.

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Josh Luebker ran commercial construction projects before he ran the numbers behind them, on data centres, military bases, hospitals, and high-rises. He wrote CONTROL: The Construction Financial Operating System, which is an eight-step framework for commercial subcontractors, and it publishes on October 1, 2026. He is a master electrician who moved into the office and kept the field vocabulary.

Sulphur Prairie Operations LLC maintains the benchmark reference behind these figures. Every edition is reconciled against the newest CFMA survey release before it publishes here. Where a figure changes between editions, the older edition keeps its year in the title so a citation to it stays correct.