The change order work is done and no one signed it

The crew did the extra work and the paperwork never caught up, so the cost stays on your job.

DIRECT ANSWER

Every update to the schedule or the scope opens a change of conditions, and that opens a chance for a change order, even a $0 one. The PM documents the change, prices it from the change order estimating sheet and sends it inside the time the contract allows. If pricing takes longer than the contract allows, an email saying so keeps it from becoming a problem. If the contract sets a deadline and it passes, the cost can become the contractor's expense. Doing the work first as time and material, or on a notice to proceed, risks never getting paid and adds to the project cost.

WHAT TO DO

Three moves, in order

STEP 01
Document each change of conditions when it opens, and send the change order inside the contract's time frame.
STEP 02
Set a dollar threshold for who approves a change order before it goes out, for example the PM under $10,000, the ops manager from $10,000 to $50,000 and the COO above that.
STEP 03
Read the contract's notice and time and material language before the crew starts extra work, and ask an attorney about anything it doesn't answer.
HOW CFOS HANDLES THIS

What CFOS does about it

The foreman sees a T&M ticket on the daily, and the GC signs it on site before the crew leaves. CFOS turns the signed ticket into a change order draft with its own number, and it goes on the next pay app. If the GC never signs, the draft stays open on the PM's list, so the cost is visible instead of mixed into the job. What the contract says about notice deadlines is still yours to read.

Who owns this: Project manager.

AT YOUR SIZE

At $3M, a crew of four doing extra work for two days can erase the profit on a small job. Get the T&M ticket signed the same day, even if the price is still open. Then send the priced change order inside the time your contract allows.

Every Monday we email the list what we built that week, with screenshots or a short video, and we email you the day it opens. Your address stays with Run On CFOS. One click unsubscribes.

Early access offer: everyone on this list before CFOS for QuickBooks opens gets 12 months with no subscription fee, counted from the day it opens in January 2027. During those 12 months the only charge is AI use, billed every Monday at what it costs us plus 10 percent for the work of billing it. Pay by bank transfer (ACH) and that is the whole charge, and pay by card and 3 percent is added for the card fee. After the 12 months the regular monthly price for your size starts, and you can cancel anytime before then with nothing owed but the AI you used.

30 days free, a 90-day money-back guarantee, and cancel anytime. It opens January 2027. We email you every Monday with what we built, and the day it opens.

TRAINING

Learn this part of the job

SPM The Construction CFO publishes this course. It's a separate company from this one, and the course is on its own school site.

QUESTIONS

What owners ask

Can I make a GC pay for change order work with no signed change order?

The crew did the extra work and the paperwork never caught up, so the cost stays on your job. Every update to the schedule or the scope opens a change of conditions, and that opens a chance for a change order, even a $0 one. The PM documents the change, prices it from the change order estimating sheet and sends it inside the time the contract allows. If pricing takes longer than the contract allows, an email saying so keeps it from becoming a problem. If the contract sets a deadline and it passes, the cost can become the contractor's expense. Doing the work first as time and material, or on a notice to proceed, risks never getting paid and adds to the project cost.

Which part of the system fixes this?

The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It's drawn from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.

Is this normal for my trade?

Across the 48 trades that publish a figure, net profit at $1M to $5M averages 7% before taxes. If you're well under that and this page describes your month, the two are usually the same story. The published average tells you where the pack is, and your own job costing tells you where you are, which is the number that pays payroll.

Where do I start?

Document each change of conditions when it opens, and send the change order inside the contract's time frame.

Can I fix this without touching anything else?

You can try, and it doesn't hold. Step 06 depends on step 04, estimating system. Install it ahead of that and it produces numbers the field won't trust, which is worse than the problem you started with.

WATCH
WEBINAR · OCTOBER 28, 2026

Year-End Starts Before December: Amy Houk and Josh Luebker

December doesn't create payment problems. It just makes the ones we've been ignoring a whole lot harder to fix.

WATCH THE WEBINAR
AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.