Late 811 locates bill you twice
You can't legally dig until someone else marks the utilities, and if the marks are wrong you pay for the strike.
A third party you can't schedule decides whether your crew can dig. It fails both ways. Late marks put a crew and its iron on standby with nothing to charge, and wrong marks put a damage claim on you. Underground utility work has both risks, and usually neither one is in the estimate. Owners absorb both costs for years without seeing them split out.
Three moves, in order
What CFOS does about it
The foreman's daily records the crew, equipment and photos, so an idle crew waiting on marks is recorded the same day. A T&M ticket goes on the daily and the GC signs it on site, which turns standby into a change order draft. You log the ticket dates and mark dates yourself, and the standby language in the contract stays your negotiation.
Who owns this: Project manager and foreman.
At $4M, one late locate can idle a crew and a machine for days. Photograph the marks and note the dates on the daily each time. At $20M, make the standby notice part of the PM's checklist before the first ticket goes in.
90 days free, a 90-day money-back guarantee, and cancel anytime. It opens January 2027.
Step 06: Project management
Billing dates, change orders, and notices, written as standards that work without anyone following up on them.
Other problems step 06 solves
Other things that go wrong
What owners ask
How do I bill for standby time when 811 locates are late or wrong?
You can't legally dig until someone else marks the utilities, and if the marks are wrong you pay for the strike. A third party you can't schedule decides whether your crew can dig. It fails both ways. Late marks put a crew and its iron on standby with nothing to charge, and wrong marks put a damage claim on you. Underground utility work has both risks, and usually neither one is in the estimate. Owners absorb both costs for years without seeing them split out.
Which part of the system fixes this?
The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It's drawn from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.
Does this only happen in underground utility?
Effectively yes, and that's why it has its own page. Underground utility belongs to civil and earthwork and has 3% net profit at $1M to $5M. The mechanism behind this problem has no real analog in the other 47 trades, so the general advice doesn't fit it.
Where do I start?
Log the ticket date, the expected mark date, the date the marks appeared and the crew hours idle on every dig. That makes standby a documented number.
Can I fix this without touching anything else?
You can try, and it doesn't hold. Step 06 depends on step 04, estimating system. Install it ahead of that and it produces numbers the field won't trust, which is worse than the problem you started with.
