CFOS for QuickBooks, coming January 2027See what you get
CFOS-06PROJECT MANAGEMENT
THE PROBLEM · FIXED BY STEP 06 · KNOW YOUR COSTS

You can't release for fab until someone else approves

The submittal has been on the engineer's desk for five weeks. The lead time didn't pause while it waited there.

DIRECT ANSWER

Nothing is released for fabrication until the submittal comes back approved, and the design team controls that clock. Every week it waits adds a week to a lead time that was already the longest item on your schedule. You can't see the delay in your job cost until the gear misses its date and the acceleration starts. Most contracts give the reviewer a set review period. Almost no contractor checks the return date against it.

WHAT TO DO

Three moves, in order

STEP 01
Log the submitted date and the contractual review period for every submittal, then record the date it comes back and circulate the aging list weekly.
STEP 02
Write the notice the day a review period is exceeded, because a time extension you didn't ask for at the time isn't available later.
STEP 03
Tie each submittal to the lead time it gates, so a late approval reads as a schedule number.
HOW CFOS HANDLES THIS

What CFOS does about it

CFOS tracks submittals as items on the job, so the aging list is a screen and isn't a spreadsheet. Pay app due dates and PM reminders are separate, but the same PM sees both. The contractual review period and the notice letter are yours to write.

Who owns this: Project manager.

AT YOUR SIZE

At $5M, a submittal waiting on the engineer for weeks can push gear past its date. Log the submitted date and the review period for each one, and write notice the day it's exceeded. At $20M, give each PM a weekly aging list and review the oldest items together.

90 days free, a 90-day money-back guarantee, and cancel anytime. It opens January 2027.

QUESTIONS

What owners ask

Submittal approval delays holding up electrical fabrication and schedule?

The submittal has been on the engineer's desk for five weeks. The lead time didn't pause while it waited there. Nothing is released for fabrication until the submittal comes back approved, and the design team controls that clock. Every week it waits adds a week to a lead time that was already the longest item on your schedule. You can't see the delay in your job cost until the gear misses its date and the acceleration starts. Most contracts give the reviewer a set review period. Almost no contractor checks the return date against it.

Which part of the system fixes this?

The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It's drawn from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.

Does this only happen in electrical?

Effectively yes, and that's why it has its own page. Electrical belongs to electrical and technology and has 9% net profit at $1M to $5M. The mechanism behind this problem has no real analog in the other 47 trades, so the general advice doesn't fit it.

Where do I start?

Log the submitted date and the contractual review period for every submittal, then record the date it comes back and circulate the aging list weekly.

Can I fix this without touching anything else?

You can try, and it doesn't hold. Step 06 depends on step 04, estimating system. Install it ahead of that and it produces numbers the field won't trust, which is worse than the problem you started with.

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.