SWPPP AND EROSION CONTROL · CIVIL AND EARTHWORK · FIXED BY STEP 03

Weather owns your repair schedule; the permit owns the clock

It rains Tuesday night, the crew is out fixing fence Wednesday morning, and there's no pay item anywhere for that truck.

WHY IT'S A SWPPP AND EROSION CONTROL PROBLEM

No other trade has a contractual repair deadline measured in business days off a rainfall event, applying continuously from grubbing through NOT. A drywall crew that misses a Wednesday is behind schedule. You're out of compliance, and the notice of violation goes against the owner's permit, which is why you fund availability itself even though a bid form has no unit for it.

WHAT IT COSTS

The size of it

One two-man crew with a truck on standby costs roughly $18K to $22K a month fully burdened. Fold it into job cost and your jobs look randomly unprofitable by rainfall; leave it out of the bid rate and you're short that number every wet month.

OVERHEAD AT $1M to $5M
14%
CFOS target 13% for SWPPP and erosion control.
GROSS MARGIN AT $1M to $5M
24%
CFOS target 26.5% for SWPPP and erosion control.
NET PROFIT AT $1M to $5M
10%
CFOS target 13.5% for SWPPP and erosion control.

The Construction General Permit says routine maintenance deficiencies found at inspection get initiated immediately and completed by the close of the next business day, with seven calendar days as the documented exception. That clock applies for the entire life of the job and the trigger is weather. You can't forecast a storm into a crew plan six weeks out, so the only way to meet the deadline is holding a truck and two guys available for events that may never come. Reserve capacity isn't chargeable to any single job, and every bid you wrote assumed it existed.

WHAT TO DO

Three moves, in order

STEP 01
Pull the standby crew and truck out of job cost and give them their own overhead line, so a wet month stops making one job look like a loser.
STEP 02
Go back twelve months and count the storm deploys per month. That count is your real reserve requirement, not a feeling about the weather.
STEP 03
Recover the cost where the exposure lives: a per-site-per-month compliance rate on maintenance contracts, and a loading on installed BMP unit prices for jobs with long open-dirt periods.
QUESTIONS

What SWPPP and erosion control owners ask

How do I price the crew I keep on standby for storm BMP repairs?

It rains Tuesday night, the crew is out fixing fence Wednesday morning, and there's no pay item anywhere for that truck.

What does it cost?

One two-man crew with a truck on standby costs roughly $18K to $22K a month fully burdened. Fold it into job cost and your jobs look randomly unprofitable by rainfall; leave it out of the bid rate and you're short that number every wet month.

What do I do first?

Pull the standby crew and truck out of job cost and give them their own overhead line, so a wet month stops making one job look like a loser.

What are SWPPP and erosion control contractors supposed to be making?

SWPPP and erosion control has 24% gross margin, 14% overhead and 10% net profit after taxes at $1M to $5M. The all-trade average is 7%, so this trade is 3 points above it. The CFOS target is 13.5%.

Which part of the system fixes it?

The step is number 03, overhead calculation. What indirect cost really comes to at your size, and the rate your estimating template should be using. It comes from chapter 3 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for SWPPP and erosion control contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for SWPPP and erosion control contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.