Bid pounds and bought pounds are two different numbers

You bid 42,000 pounds of duct and the mill invoices add up to 51,000, and there is nothing in the building that tells you where the other 9,000 pounds went.

WHY IT'S AN HVAC PROBLEM

Most trades bid and buy in the same unit, so a material overrun is easy to trace. You bid a finished installed weight and buy a raw coil weight. The difference comes from how the shop nests and the fitting mix, and the estimate never sees it. So the overrun turns up as a lump with no cause attached, on the largest commodity you handle.

WHAT IT COSTS

The size of it

You have a 5 to 9 percent material overrun on a quarter of the job cost. It repeats on every job, and nothing catches it before the job closes.

OVERHEAD AT $1M to $5M
16%
CFOS target 15% for HVAC.
GROSS MARGIN AT $1M to $5M
24%
CFOS target 26.5% for HVAC.
NET PROFIT AT $1M to $5M
8%
CFOS target 11.5% for HVAC.

Sheet metal is 25 to 40 percent of a duct-heavy job. It's the one line item where the unit you bid and the unit you buy are different. The estimate prices installed pounds by SMACNA gauge and pressure class. You buy galvanized coil by hundredweight at whatever the mill charges that week. Drop and scrap add 10 to 20 percent, depending on fitting mix and how well the shop nests. Say your waste factor is a number somebody typed in 2019 and this job had 22 percent drop. Nothing catches it, because pounds installed and pounds bought never appear in the same report. Add galvanized price moves between bid and buyout. Now the biggest commodity on the job is unmanaged from both ends.

WHAT TO DO

Three moves, in order

STEP 01
Build one report per job that puts estimated installed pounds by gauge next to coil hundredweight purchased, with the drop percentage calculated at the bottom.
STEP 02
Set waste factors by fitting mix, one for straight duct and a higher one for fitting-heavy work, and update them from the last four closed jobs.
STEP 03
Lock galvanized pricing at buyout where the supplier will do it, and where they won't, price the exposure as a stated allowance the PM can see.
QUESTIONS

What HVAC owners ask

Why did I buy more sheet metal than I bid on the job?

You bid 42,000 pounds of duct and the mill invoices add up to 51,000, and there is nothing in the building that tells you where the other 9,000 pounds went.

What does it cost?

You have a 5 to 9 percent material overrun on a quarter of the job cost. It repeats on every job, and nothing catches it before the job closes.

What do I do first?

Build one report per job that puts estimated installed pounds by gauge next to coil hundredweight purchased, with the drop percentage calculated at the bottom.

What are HVAC contractors supposed to be making?

HVAC has 24% gross margin, 16% overhead and 8% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 1 point above it. The CFOS target is 11.5%.

Which part of the system fixes it?

The step is number 04, estimating system. The estimate maps one to one onto the job cost codes, so variance means something the day it appears. It comes from chapter 4 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for HVAC contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for HVAC contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.