You bid cubic yards and pay by the ton

You bid 40,000 yards of import and every scale ticket comes back in tons. The biggest cost line on the job is measured in a unit your contract never defined.

WHY IT'S A CIVIL PROBLEM

In most trades a box of material is a box of material from the yard to the wall. Civil buys tons at the pit, pays haul by the hour or the load, and gets paid by the cubic yard at plan measure. That's three units for one pile of dirt. The conversion is in the estimator's head and never on the ticket, so no one watches the error grow.

WHAT IT COSTS

The size of it

On a $1.2M grading package, a 10% conversion error on import costs roughly $60k to $120k of material and haul with no change order behind it. Spread across hundreds of tickets, it never trips a single red flag.

OVERHEAD AT $1M to $5M
14%
CFOS target 13% for civil.
GROSS MARGIN AT $1M to $5M
21%
CFOS target 23.5% for civil.
NET PROFIT AT $1M to $5M
7%
CFOS target 10.5% for civil.

Pick one unit and track the whole job in it. You bid excavation and embankment by the cubic yard at plan or bank measure. You buy select fill, flex base, and stone by the ton FOB the pit, and pay haul by the hour or the load. So your bid and your cost report use different units from day one. Between them is a shrink and swell factor and a unit weight your estimator assumed once. If no one checks both against scale tickets in the first week of import, the error grows on every load for the rest of the job. Set the import cost codes to record both sides: tons received and cubic yards placed, converted at the factor you bid. Then you can read Tuesday's tickets and know whether you're ahead of the yardage or buying somebody else's dirt without seeing it.

WHAT TO DO

Three moves, in order

STEP 01
Pull last week's scale tickets, total the tons, and divide by the cubic yards your grade checker says went in the ground. That ratio is your real unit weight and swell. Compare it to the one in the bid.
STEP 02
Rebuild the import cost codes so each one tracks tons received and cubic yards placed side by side, with the bid conversion factor stored on the code itself.
STEP 03
Set a recurring Friday check on the first 20% of the import. If tons per placed yard differ from the bid factor by more than 5%, reprice the balance and go get the change order while the dirt is still moving.
QUESTIONS

What civil owners ask

I bid cubic yards but my fill is billed in tons and I can't tell if I'm making money?

You bid 40,000 yards of import and every scale ticket comes back in tons. The biggest cost line on the job is measured in a unit your contract never defined.

What does it cost?

On a $1.2M grading package, a 10% conversion error on import costs roughly $60k to $120k of material and haul with no change order behind it. Spread across hundreds of tickets, it never trips a single red flag.

What do I do first?

Pull last week's scale tickets, total the tons, and divide by the cubic yards your grade checker says went in the ground. That ratio is your real unit weight and swell. Compare it to the one in the bid.

What are civil contractors supposed to be making?

Civil has 21% gross margin, 14% overhead and 7% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.

Which part of the system fixes it?

The step is number 04, estimating system. The estimate maps one to one onto the job cost codes, so variance means something the day it appears. It comes from chapter 4 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for civil contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for civil contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.