CFOS for QuickBooks, coming January 2027See what you get
HVACCFOS-07
HVAC · MECHANICAL AND LIFE SAFETY · FIXED BY STEP 07

Retention depends on a report you didn't write

Field work wrapped in April, and your last five percent is still waiting on a heating verification somebody has to schedule for cold weather.

WHY IT'S AN HVAC PROBLEM

Other trades finish, get inspected, and clear retention on their own schedule. Your money is released by a report from an agency you don't hire, don't schedule, and can't staff up. The system has to be tested in weather that may be six months away. Adding manpower does nothing. That's what makes this different from every other closeout problem on the job.

WHAT IT COSTS

The size of it

You wait 6 to 18 months past your last day of field work for 5 to 10 percent of contract value, and no amount of added labor buys you out of it.

OVERHEAD AT $1M to $5M
16%
CFOS target 15% for HVAC.
GROSS MARGIN AT $1M to $5M
24%
CFOS target 26.5% for HVAC.
NET PROFIT AT $1M to $5M
8%
CFOS target 11.5% for HVAC.

You're on site from underground condensate and roof curbs in month two through start-up, TAB, controls point-to-point, and commissioning in the final month. Few trades on the job are there longer. Your final release doesn't depend on your own work. Two third-party reports control it, one from the test and balance agency and one from the commissioning authority. Sometimes the owner hires both directly. The CxA writes issues, you correct them, and the CxA checks again at the next site visit, whenever that is. A lot of specs also require seasonal testing. You can't verify heating capacity in July, so final acceptance waits for the opposite season.

WHAT TO DO

Three moves, in order

STEP 01
Before signing, get the TAB and Cx scope in writing: who hires them, when they mobilize, how re-verification gets scheduled, and what the spec says about seasonal testing.
STEP 02
Track retention as its own receivable with an expected release month set by the commissioning schedule, and put it on the rolling cash forecast so it stops being a surprise.
STEP 03
Ask for partial retention release at substantial completion on everything the Cx report doesn't gate, and leave only a seasonal testing holdback behind.
QUESTIONS

What HVAC owners ask

How long can a GC hold retainage waiting on commissioning?

Field work wrapped in April, and your last five percent is still waiting on a heating verification somebody has to schedule for cold weather.

What does it cost?

You wait 6 to 18 months past your last day of field work for 5 to 10 percent of contract value, and no amount of added labor buys you out of it.

What do I do first?

Before signing, get the TAB and Cx scope in writing: who hires them, when they mobilize, how re-verification gets scheduled, and what the spec says about seasonal testing.

What are HVAC contractors supposed to be making?

HVAC has 24% gross margin, 16% overhead and 8% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 1 point above it. The CFOS target is 11.5%.

Which part of the system fixes it?

The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for HVAC contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for HVAC contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.