Retention rides on a report you didn't write
Field work wrapped in April, and your last five percent is still waiting on a heating verification somebody has to schedule for cold weather.
Other trades finish, get inspected, and clear retention on their own schedule. Your money is released by a document written by an agency you don't hire, don't schedule, and can't staff up, on a system that has to be tested in weather that may be six months away. Adding manpower does nothing, which is what makes this different from every other closeout problem on the job.
The size of it
You wait 6 to 18 months past your last day of field work for 5 to 10 percent of contract value, and no amount of added labor buys you out of it.
You're on site from underground condensate and roof curbs in month two through start-up, TAB, controls point-to-point, and commissioning in the final month, one of the longest spans of any trade on the job. The final release doesn't turn on your own work at all. Two third-party reports control it, one from the test and balance agency and one from the commissioning authority, and sometimes the owner hires both directly. The CxA writes issues, you correct them, and the CxA re-verifies whenever the next site visit happens. A lot of specs also require seasonal testing, and since you can't verify heating capacity in July, final acceptance waits for the opposite season.
Three moves, in order
Step 07: Monthly cadence
Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month.
What else costs hvac contractors money
The same mechanism in other trades
What hvac owners ask
How long can a gc hold retainage waiting on commissioning?
Field work wrapped in April, and your last five percent is still waiting on a heating verification somebody has to schedule for cold weather.
What does it cost?
You wait 6 to 18 months past your last day of field work for 5 to 10 percent of contract value, and no amount of added labor buys you out of it.
What do I do first?
Before signing, get the TAB and Cx scope in writing: who hires them, when they mobilize, how re-verification gets scheduled, and what the spec says about seasonal testing.
What are hvac contractors supposed to be making?
HVAC runs 24% gross margin, 16% overhead and 8% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 1 points above it. The CFOS target is 11%.
Which part of the system fixes it?
The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: The Construction Financial Operating System.
