TANK AND VESSEL · SPECIALTY · FIXED BY STEP 04

You Sell in Gallons and Buy in Pounds

Seismic revisions bumped two shell courses, your plate order grew by 25,000 pounds, and the owner still calls it a 500,000-gallon tank.

WHY IT'S A TANK AND VESSEL PROBLEM

Most trades sell in roughly the unit they buy in: square feet of board, feet of conduit, and cubic yards placed. A tank is sold in gallons, bought in pounds, and built in weld inches, and nothing in the estimate, the contract, or the pay app is denominated in the unit the money moves in. That missing translation is why a design revision can take your margin without ever looking like a change to anyone reviewing it.

WHAT IT COSTS

The size of it

An eighth-inch bump on two shell courses adds 20,000 to 30,000 pounds of plate and several hundred weld inches, $40K to $70K of cost, and the change order gets denied because the deliverable is still a 500,000-gallon tank.

OVERHEAD AT $1M to $5M
15%
CFOS target 14% for tank and vessel.
GROSS MARGIN AT $1M to $5M
23%
CFOS target 25.5% for tank and vessel.
NET PROFIT AT $1M to $5M
8%
CFOS target 11.5% for tank and vessel.

Capacity is what gets specified, so the contract says 500,000 gallons. Your estimator turns that into a shell configuration and prices roughly 340,000 pounds of plate. Shell course thickness comes from seismic design category, wind speed, product specific gravity, and corrosion allowance, and a revision to any one of those changes the pounds and the weld inches while the gallons stay where they started. Labor has the same mismatch: crews are productive in weld inches or diameter inches deposited, while the schedule of values is written as lump-sum percent-complete of a tank.

WHAT TO DO

Three moves, in order

STEP 01
Convert every tank estimate to pounds of plate and weld inches, and print the seismic category, wind speed, specific gravity, and corrosion allowance you assumed on the face of the bid.
STEP 02
Build the schedule of values around tonnage set and weld inches deposited so progress billing tracks the unit your cost moves in.
STEP 03
Put a written re-price trigger in the contract: any change to seismic design category, product specific gravity, or corrosion allowance reopens plate tonnage and weld quantity. Get it signed before the first submittal.
QUESTIONS

What tank and vessel owners ask

Tank bid in gallons but plate priced by the pound?

Seismic revisions bumped two shell courses, your plate order grew by 25,000 pounds, and the owner still calls it a 500,000-gallon tank.

What does it cost?

An eighth-inch bump on two shell courses adds 20,000 to 30,000 pounds of plate and several hundred weld inches, $40K to $70K of cost, and the change order gets denied because the deliverable is still a 500,000-gallon tank.

What do I do first?

Convert every tank estimate to pounds of plate and weld inches, and print the seismic category, wind speed, specific gravity, and corrosion allowance you assumed on the face of the bid.

What are tank and vessel contractors supposed to be making?

Tank and vessel has 23% gross margin, 15% overhead and 8% net profit after taxes at $1M to $5M. The all-trade average is 7%, so this trade is 1 point above it. The CFOS target is 11.5%.

Which part of the system fixes it?

The step is number 04, estimating system. The estimate maps one to one onto the job cost codes, so variance means something the day it appears. It comes from chapter 4 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for tank and vessel contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for tank and vessel contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.