CFOS for QuickBooks, coming January 2027See what you get
CFOS-04ESTIMATING SYSTEM
THE PROBLEM · FIXED BY STEP 04 · KEEP YOUR PROFIT

Estimating turns the job over and the PM starts cold

The estimator knows why the numbers are what they are, and the PM finds out in month three.

DIRECT ANSWER

The handoff is a meeting, and it comes once the team is chosen. Operations assigns the PM, a superintendent and a field team, and estimating tells operations the estimate is won. The PM, the estimator, the business developer and the superintendent are required. Assistant PMs, project engineers, foremen and junior estimators can attend to learn. The estimator does a page flip: what's being installed where, how it was bid, the thinking behind manpower and execution, holes in the estimate, risk, low bids from subs and vendors, and the estimated equipment. Estimating then introduces the PM to the client.

WHAT TO DO

Three moves, in order

STEP 01
Schedule the handoff meeting as soon as operations chooses the project team.
STEP 02
Have the estimator go through the whole estimate page by page, with the holes and the risks said out loud.
STEP 03
Have estimating introduce the PM to the client, ideally after the meeting.
HOW CFOS HANDLES THIS

What CFOS does about it

Once the bid is won, it becomes a job in CFOS with its contract value. The estimate comes in as the job budget by cost code, so the PM starts with the estimator's numbers instead of a blank page. Contracts and spec books are read and the terms are pulled out for the PM. The handoff meeting is still a conversation between people, and CFOS keeps what was said where the PM can find it.

Who owns this: Estimator and project manager.

AT YOUR SIZE

At $5M, the estimator and the PM may be the same person or two people at a desk apart. Hold a 30 minute meeting once the job is won. Walk through the risks, the low sub bids and the equipment in the estimate.

Every Monday we email the list what we built that week, with screenshots or a short video, and we email you the day it opens. Your address stays with Run On CFOS. One click unsubscribes.

Early access offer: everyone on this list before CFOS for QuickBooks opens gets 12 months with no subscription fee, counted from the day it opens in January 2027. During those 12 months the only charge is AI use, billed every Monday at what it costs us plus 10 percent for the work of billing it. Pay by bank transfer (ACH) and that is the whole charge, and pay by card and 3 percent is added for the card fee. After the 12 months the regular monthly price for your size starts, and you can cancel anytime before then with nothing owed but the AI you used.

30 days free, a 90-day money-back guarantee, and cancel anytime. It opens January 2027. We email you every Monday with what we built, and the day it opens.

TRAINING

Learn this part of the job

SPM The Construction CFO publishes this course. It's a separate company from this one, and the course is on its own school site.

QUESTIONS

What owners ask

Who is responsible for estimate to project handoff in construction?

The estimator knows why the numbers are what they are, and the PM finds out in month three. The handoff is a meeting, and it comes once the team is chosen. Operations assigns the PM, a superintendent and a field team, and estimating tells operations the estimate is won. The PM, the estimator, the business developer and the superintendent are required. Assistant PMs, project engineers, foremen and junior estimators can attend to learn. The estimator does a page flip: what's being installed where, how it was bid, the thinking behind manpower and execution, holes in the estimate, risk, low bids from subs and vendors, and the estimated equipment. Estimating then introduces the PM to the client.

Which part of the system fixes this?

The step is number 04, estimating system. The estimate maps one to one onto the job cost codes, so variance means something the day it appears. It's drawn from chapter 4 of CONTROL: C.F.O.S. Construction Financial Operating System.

Is this normal for my trade?

Across the 48 trades that publish a figure, net profit at $1M to $5M averages 7% before taxes. If you're well under that and this page describes your month, the two are usually the same story. The published average tells you where the pack is, and your own job costing tells you where you are, which is the number that pays payroll.

Where do I start?

Schedule the handoff meeting as soon as operations chooses the project team.

Can I fix this without touching anything else?

You can try, and it doesn't hold. Step 04 depends on step 01, job cost structure and step 03, overhead calculation. Install it ahead of those and it produces numbers the field won't trust, which is worse than the problem you started with.

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.