CFOS for QuickBooks, coming January 2027See what you get
DEWATERINGCFOS-07
DEWATERING · CIVIL AND EARTHWORK · FIXED BY STEP 07

The Whole System Operates Before Invoice One

Wellpoints, header, pumps, tanks, and fuel are all in play before there's anything to bill, and then you wait 30 days to invoice and longer to get paid.

WHY IT'S A DEWATERING PROBLEM

Trades that install as they go spend about what they bill each month, so their cash follows the work. Dewatering puts the whole system in up front. After that, calendar time turns into fuel and rental with no new installed work to point at. So peak cash out and zero cash in fall in the same month on every job. That's why this trade's close calls on payroll come at the front of the schedule.

WHAT IT COSTS

The size of it

On a normal deployment you're funding the full system, the permit fees, the design, and the survey, plus daily fuel and rental, for 30 days before an invoice exists and longer before cash comes in.

OVERHEAD AT $1M to $5M
14%
Derived from Excavation, the nearest comparable trade. CFOS target 13%.
GROSS MARGIN AT $1M to $5M
21%
Derived from Excavation, the nearest comparable trade. CFOS target 23.5%.
NET PROFIT AT $1M to $5M
7%
Derived from Excavation, the nearest comparable trade. CFOS target 10.5%.

Dewatering sets up completely on day one and then keeps pumping. Before the first pay app goes out, you've paid for wellpoints and sock sand, HDPE header and the full discharge line, and rented vacuum pump sets or submersibles with generators. Add settling or frac tanks where turbidity limits apply, permit and application fees, the hydrogeologic work behind the design, and a pre-condition survey of the neighboring structures. Once it starts, fuel and rental add up every hour of every day. Then you wait 30 days to invoice and longer to collect behind pay-when-paid. The bigger the job, the more cash the front end takes.

WHAT TO DO

Three moves, in order

STEP 01
Price the day-one cash stack as its own number before you sign: wellpoints and sock sand, header and discharge line, pump and generator rental, frac or settling tanks, permit and application fees, hydrogeologic design, and pre-condition survey. That figure is what the job asks you to lend it.
STEP 02
Ask for a mobilization payment or stored-materials billing at buyout, and get the first pay app date and the pay-when-paid terms in writing before the equipment leaves the yard.
STEP 03
Keep a rolling 13-week cash forecast keyed to pump-days and gallons of fuel per week per job, and review it the same week every month so the crunch is visible before payroll comes due.
QUESTIONS

What dewatering owners ask

Why is dewatering cash flow worst in the first month of a job?

Wellpoints, header, pumps, tanks, and fuel are all in play before there's anything to bill, and then you wait 30 days to invoice and longer to get paid.

What does it cost?

On a normal deployment you're funding the full system, the permit fees, the design, and the survey, plus daily fuel and rental, for 30 days before an invoice exists and longer before cash comes in.

What do I do first?

Price the day-one cash stack as its own number before you sign: wellpoints and sock sand, header and discharge line, pump and generator rental, frac or settling tanks, permit and application fees, hydrogeologic design, and pre-condition survey. That figure is what the job asks you to lend it.

What are dewatering contractors supposed to be making?

No survey separates dewatering, so there is no figure of its own. The nearest comparable trade in the reference is Excavation, which has 21% gross margin, 14% overhead and 7% net profit before taxes at $1M to $5M, with a CFOS target of 10.5% net. Those are derived figures, not dewatering's own. Read them as the neighbourhood, and read your own job costing as the answer.

Which part of the system fixes it?

The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for dewatering contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What SPM The Construction CFO does, and what it costs

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.