The Scale Wants Cash Today, The GC Pays In Sixty Days
Almost everything a demolition job costs goes out in the first two weeks, and the first pay application hasn't even been submitted yet.
Other trades spend across the whole job and bill along the way. Demolition spends most of its cash in the opening two weeks and then waits on pay-when-paid terms. No other trade has that ratio of front-loaded cash out to contract value. The shorter the job, the worse it gets.
The size of it
You have ninety plus days of negative cash on a five week job, and the low point comes in the week the scale tickets and the float invoices come due together.
Fund the job before you take it, and size the hole first. Tipping is a same-day, per-load transaction paid at the scale, and it's usually your largest single cost line. Add the rest of the front-loaded spend: lowbed float charges both directions on every machine, roll-off delivery deposits, permits, utility disconnect fees, temporary fencing, a water truck for dust suppression, and an abatement sub asking for a deposit. Nearly all of that leaves the bank in the first two weeks. Your first pay application goes in at the end of month one and funds 45 to 60 days after that. Ninety plus days of negative cash on a job that's only on site for five weeks is where the AP pile and the near-miss on payroll come from.
Three moves, in order
Step 03: Overhead calculation
What indirect cost really comes to at your size, and the rate your estimating template should be using.
What else costs demolition contractors money
The same mechanism in other trades
What demolition owners ask
How do I cover landfill and mobilization costs before the first pay app funds?
Almost everything a demolition job costs goes out in the first two weeks, and the first pay application hasn't even been submitted yet.
What does it cost?
You have ninety plus days of negative cash on a five week job, and the low point comes in the week the scale tickets and the float invoices come due together.
What do I do first?
Draw a week-by-week cash curve for each job before you sign: tipping, floats, permits, fencing, and subs against projected pay app funding dates. The bottom of that curve is what the job has to borrow.
What are demolition contractors supposed to be making?
Demolition has 20% gross margin, 16% overhead and 4% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 3 points below it. The CFOS target is 10%.
Which part of the system fixes it?
The step is number 03, overhead calculation. What indirect cost really comes to at your size, and the rate your estimating template should be using. It comes from chapter 3 of CONTROL: C.F.O.S. Construction Financial Operating System.
Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for demolition contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.
