You Finish In Month Two And Get Paid In Month Twenty Six
The foundation was wrapped and buried last March, and the retainage is still sitting with the GC. The trade with the shortest time on site holds the money the longest.
Every sub deals with retention, but most of them are still on site while it accrues and finish near the release date. Below grade waterproofing is complete, covered, and invisible in the first quarter of a multi-year job, so your cash is tied to punch work on floors that didn't exist when you left. The warranty start date compounds it, because the clock on your longest liability is set by a certificate you don't sign.
The size of it
On a $600K below grade scope, roughly $30K to $60K sits unreleased for two years while you fund the next three jobs out of working capital. The balance sheet also carries a long-tail warranty obligation whose start date somebody else controls.
Retention of 5 to 10% comes out of your month-two progress payments and gets released at substantial completion, which on a two-year build is 18 to 30 months later. Between those two dates, trades that hadn't even mobilized when your membrane was backfilled have to finish their punch before your money moves. The warranty runs the same direction: a manufacturer's 10, 15, or 20 year system warranty is dated from substantial completion, so a wall you installed in month two carries exposure out to month 140 and past it. You finished first and you're last in line on both counts.
Three moves, in order
Step 07: Monthly cadence
Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month.
What else costs waterproofing contractors money
The same mechanism in other trades
What waterproofing owners ask
When does retainage get released on below grade waterproofing?
The foundation was wrapped and buried last March, and the retainage is still sitting with the GC. The trade with the shortest time on site holds the money the longest.
What does it cost?
On a $600K below grade scope, roughly $30K to $60K sits unreleased for two years while you fund the next three jobs out of working capital. The balance sheet also carries a long-tail warranty obligation whose start date somebody else controls.
What do I do first?
Carry retention receivable as its own balance sheet line by job with an expected release date, and put it on the monthly close agenda so you always know what sits where.
What are waterproofing contractors supposed to be making?
Waterproofing runs 26% gross margin, 17% overhead and 9% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 2 points above it. The CFOS target is 11%.
Which part of the system fixes it?
The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: The Construction Financial Operating System.
