Four Clocks Decide When You Can Start, Cover, Or Bill
Crew is on site, membrane is on the ground, and the envelope consultant flies in Thursday. Four approvals come between your people and a billable square foot, and you hold none.
Plenty of trades wait on inspection. Waterproofing waits before it can start, again before it can cover its own work, and again before the deck above it can go ahead. The third-party consultant bills by the trip and flies in from somewhere else. Miss the observation window and finished, covered work gets dug back up. Almost no other scope has that penalty.
The size of it
Crews wait at full burdened cost with no line item to bill against, and two standby days a month on a four-man crew is roughly $6,000 to $9,000 of unrecovered labor. Your books read it as a productivity problem when the cause was an owner-caused delay.
Substrate acceptance comes first. The concrete has to be cured and dry, and a curing compound or form release the concrete sub picked can disqualify the surface outright. Next is a field mock-up, built and accepted by the architect or a registered envelope consultant before production work releases. Nothing gets backfilled or covered until an IIBEC-credentialed observer or ABAA field auditor signs off. Then the decks get a 24 to 48 hour flood test per ASTM D5957, scheduled by the GC and witnessed by the consultant. That's four calendars, and you control none of them. Your crew is on the job for all of it.
Three moves, in order
Step 01: Job cost structure
Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words.
What else costs waterproofing contractors money
The same mechanism in other trades
What waterproofing owners ask
Waterproofing crew standby waiting on envelope consultant?
Crew is on site, membrane is on the ground, and the envelope consultant flies in Thursday. Four approvals come between your people and a billable square foot, and you hold none.
What does it cost?
Crews wait at full burdened cost with no line item to bill against, and two standby days a month on a four-man crew is roughly $6,000 to $9,000 of unrecovered labor. Your books read it as a productivity problem when the cause was an owner-caused delay.
What do I do first?
Set up standby and mock-up as their own cost codes at job setup, so idle days get recorded with a date and a cause and stay out of install labor.
What are waterproofing contractors supposed to be making?
Waterproofing has 26% gross margin, 17% overhead and 9% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 2 points above it. The CFOS target is 12.5%.
Which part of the system fixes it?
The step is number 01, job cost structure. Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words. It comes from chapter 1 of CONTROL: C.F.O.S. Construction Financial Operating System.
Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for waterproofing contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.
