CFOS for QuickBooks, coming January 2027See what you get
WATERPROOFINGCFOS-02
WATERPROOFING · ENVELOPE AND STRUCTURE · FIXED BY STEP 02

You Priced Two Trips And You Made Eight

You're back at the same building for the eighth time on one square foot number. The bid unit is square feet installed and the cost unit is mob-days and kettle-days.

WHY IT'S A WATERPROOFING PROBLEM

A trade that comes to the site once can spread mobilization across the whole contract. Waterproofing comes back to the same address five to eight times over two years, when the GC is ready. It brings a piece of equipment with a fixed daily cost floor and no partial setup. That unit of measure mismatch belongs to this scope, and one contract line makes all of it impossible to see.

WHAT IT COSTS

The size of it

A contractor averaging six mobilizations on a job priced for two is absorbing $15K to $25K of unrecovered mobilization and kettle time per project. It reads as high labor in the P&L when the real problem is in how the bid was structured.

OVERHEAD AT $1M to $5M
17%
CFOS target 16% for waterproofing.
GROSS MARGIN AT $1M to $5M
26%
CFOS target 28.5% for waterproofing.
NET PROFIT AT $1M to $5M
9%
CFOS target 12.5% for waterproofing.

Waterproofing on a job like this is a sequence. Footings and below grade walls, under-slab pre-applied, elevator pit and sump, podium and plaza deck, and above grade air and vapor barrier with window transitions. Then planter and split-slab, traffic coating in the garage after everyone stops parking in it, and sealants at closeout. Each is a separate mobilization with setup, safety, staging and demob, spread across two years. Hot rubberized asphalt puts a floor under the cost. A kettle takes 3 to 5 hours to bring 400 degree material up to melt temperature. The melter, generator and hose crew use a full day whether the deck is 500 square feet or 5,000. Price the whole scope at one lump sum square foot number and the small trips lose money from the day they're scheduled.

WHAT TO DO

Three moves, in order

STEP 01
Break the bid into the trips the job really takes: footings and walls, under-slab, pit and sump, podium deck, air barrier and window transitions, planters, traffic coating, and closeout sealants. Price a mobilization on each one.
STEP 02
Set a kettle day rate that covers melt time, the melter, the generator, and the hose crew, and apply it per day regardless of how much deck is going down.
STEP 03
Give every mobilization its own cost code so the fourth remob shows you its own margin the week it happens, not at job close.
QUESTIONS

What waterproofing owners ask

How to price waterproofing remobilizations on a long job?

You're back at the same building for the eighth time on one square foot number. The bid unit is square feet installed and the cost unit is mob-days and kettle-days.

What does it cost?

A contractor averaging six mobilizations on a job priced for two is absorbing $15K to $25K of unrecovered mobilization and kettle time per project. It reads as high labor in the P&L when the real problem is in how the bid was structured.

What do I do first?

Break the bid into the trips the job really takes: footings and walls, under-slab, pit and sump, podium deck, air barrier and window transitions, planters, traffic coating, and closeout sealants. Price a mobilization on each one.

What are waterproofing contractors supposed to be making?

Waterproofing has 26% gross margin, 17% overhead and 9% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 2 points above it. The CFOS target is 12.5%.

Which part of the system fixes it?

The step is number 02, equipment cost basis. A correct internal rate per machine covering ownership, maintenance, fuel, and transport, charged to the projects that used it. It comes from chapter 2 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for waterproofing contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for waterproofing contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.