TILT-UP · CONCRETE AND MASONRY · FIXED BY STEP 02

The longest lead item is a date on a crane calendar

The crane is booked for the 14th and the cylinder results decide whether you can use it. Standby costs are yours either way.

WHY IT'S A TILT-UP PROBLEM

For most subs the long lead item is a product, and a product can be expedited, substituted, or air-freighted. Here the long lead item is somebody else's iron on somebody else's schedule. What has to be ready on that date is concrete strength, which answers to weather and to a break result, so you're matching a fixed calendar slot to a curve you don't fully control.

WHAT IT COSTS

The size of it

A standby day or a re-book is a five-figure hit at those day and week rates, and no change order comes attached to it.

OVERHEAD AT $1M–$5M
14%
Derived from Concrete, the nearest comparable trade. CFOS target 13%.
GROSS MARGIN AT $1M–$5M
21%
Derived from Concrete, the nearest comparable trade. CFOS target 23.5%.
NET PROFIT AT $1M–$5M
7%
Derived from Concrete, the nearest comparable trade. CFOS target 10.5%.

A pick needs a mobile crane sized to the heaviest panel, and that booking gets made weeks ahead as a fixed calendar slot you can't expedite the way you would a material order. Panels have to verify at least about 2,500 psi by cylinder break, test beam, or split cylinder before tilting starts. Only a test result proves that strength, and counting days on a calendar doesn't. A cold week, a soft break, a misplaced embed, or a windy morning puts you on standby or at the back of the queue behind everyone else who booked the same iron. Mobile crane rates in a market like Atlanta run roughly $575 to $1,975 a day and $4,000 to $13,825 a week.

WHAT TO DO

Three moves, in order

STEP 01
Put the cylinder break schedule on the same page as the crane booking and set break dates so you hold a result at least three days before the iron rolls in.
STEP 02
Budget a standby allowance as a real crane cost code with a dollar figure in it, so when you burn it you see it in the month it happened.
STEP 03
Before you confirm the pick date, walk every embed and lifting insert against the shop drawings, because a misplaced insert costs you the same day a soft break does.
QUESTIONS

What tilt-up owners ask

Crane standby cost when tilt-up panels aren't at strength on the pick date?

The crane is booked for the 14th and the cylinder results decide whether you can use it. Standby costs are yours either way.

What does it cost?

A standby day or a re-book is a five-figure hit at those day and week rates, and no change order comes attached to it.

What do I do first?

Put the cylinder break schedule on the same page as the crane booking and set break dates so you hold a result at least three days before the iron rolls in.

What are tilt-up contractors supposed to be making?

No survey separates tilt-up, so there is no figure of its own. The nearest comparable trade in the reference is Concrete, which runs 21% gross margin, 14% overhead and 7% net profit before taxes at $1M–$5M, with a CFOS target of 10.5% net. Those are derived figures, not tilt-up's own. Read them as the neighbourhood, and read your own job costing as the answer.

Which part of the system fixes it?

The step is number 02, equipment cost basis. A correct internal rate per machine covering ownership, maintenance, fuel, and transport, charged to the projects that used it. It comes from chapter 2 of CONTROL: The Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, andCONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for tilt-up contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, run by the same author.

What SPM The Construction CFO does, and what it costs

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.