SITEWORK · CIVIL AND EARTHWORK · FIXED BY STEP 02

Haul Miles Are Your Commodity Price, and They Moved

The rock price held all year. The trucking on it didn't, and then the spoil site quit taking dirt halfway through the export.

WHY IT IS A SITEWORK PROBLEM

There's no drawing revision behind a haul route change, so there's nothing to attach a change order to. The design held still and the truck didn't. Fuel adjustment clauses are standard on DOT work and almost never appear on a private site package, which leaves the sub holding the entire move between bid day and buyout.

WHAT IT COSTS

The size of it

On a 40,000 CY export, adding 15 miles each way is a six-figure swing on one job. Nothing on the plans changed, so the whole thing settles into your cost of work.

OVERHEAD AT $1M–$5M
15%
CFOS target 14% for sitework.
GROSS MARGIN AT $1M–$5M
18%
CFOS target 24% for sitework.
NET PROFIT AT $1M–$5M
3%
CFOS target 10% for sitework.

Your commodity is haul, and haul is priced per loaded mile against a radius you fixed the day you bid. Freight runs 40 to 60 percent of a delivered aggregate invoice. Add a fuel surcharge of 4 to 8 percent that floats with diesel and a $5 to $15 per ton logistics charge on top, and the stone itself is the minority of the ticket. Import select fill and export spoil both get priced off that assumed radius. When the borrow pit runs short, the spoil site fills up, or the county restricts a haul route mid-job, a five-mile round trip becomes twenty and your largest cost line roughly doubles.

WHAT TO DO

Three moves, in order

STEP 01
Write the borrow pit and the spoil site into the bid, with the round-trip mileage and tipping rate you priced, so the assumption lives on the contract and not in your head.
STEP 02
Cost-code haul apart from material on every import and export line so you can read loaded miles per cubic yard rather than a blended delivered price.
STEP 03
Ask for a haul-radius escalation clause on private work the way DOT jobs carry fuel adjustment, and check haul cycles against bid mileage weekly while the trucks are still running.
QUESTIONS

What sitework owners ask

How to price haul when the spoil site closes mid job?

The rock price held all year. The trucking on it didn't, and then the spoil site quit taking dirt halfway through the export.

What does it cost?

On a 40,000 CY export, adding 15 miles each way is a six-figure swing on one job. Nothing on the plans changed, so the whole thing settles into your cost of work.

What do I do first?

Write the borrow pit and the spoil site into the bid, with the round-trip mileage and tipping rate you priced, so the assumption lives on the contract and not in your head.

What are sitework contractors supposed to be making?

Sitework runs 18% gross margin, 15% overhead and 3% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 4 points below it. The CFOS target is 10%.

Which part of the system fixes it?

The step is number 02, equipment cost basis. A true internal rate per machine covering ownership, maintenance, fuel, and transport, charged to the projects that used it. It comes from chapter 2 of CONTROL: The Construction Financial Operating System.

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Josh Luebker ran commercial construction projects before he ran the numbers behind them, on data centres, military bases, hospitals, and high-rises. He wrote CONTROL: The Construction Financial Operating System, which is an eight-step framework for commercial subcontractors, and it publishes on October 1, 2026. He is a master electrician who moved into the office and kept the field vocabulary.

Sulphur Prairie Operations LLC maintains the benchmark reference behind these figures. Every edition is reconciled against the newest CFMA survey release before it publishes here. Where a figure changes between editions, the older edition keeps its year in the title so a citation to it stays correct.

Eight steps. Sixty days.

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It publishes on October 1, 2026. Eight steps, six working templates, and the order they install in.