SITEWORK · CIVIL AND EARTHWORK · FIXED BY STEP 07

Retention Releases When the Grass Hits Seventy Percent

Your last retention check is stuck behind seed germinating in October, and germination depends on mother nature no matter when the work finished.

WHY IT'S A SITEWORK PROBLEM

Every other trade's retention is gated by its own completion. Yours is gated by biology and a regulator's inspection, on scope that finished a year and a half earlier. Meanwhile the erosion control bond stays posted and the 7-day BMP maintenance obligation keeps running on a job that stopped producing revenue long ago.

WHAT IT COSTS

The size of it

The GC withholds 5 to 10 percent on work you performed 18 to 22 months earlier, and seeding season sets the release date. Bond and BMP maintenance cost keeps accruing the whole time.

OVERHEAD AT $1M–$5M
15%
CFOS target 14% for sitework.
GROSS MARGIN AT $1M–$5M
18%
CFOS target 24% for sitework.
NET PROFIT AT $1M–$5M
3%
CFOS target 10% for sitework.

You're on site in month one of a 12 to 24 month build, and retention releases at final acceptance, which is the widest earn-to-collect span any trade on that job has. Then a second clock stacks on top. The construction stormwater permit can't be terminated until final stabilization, commonly 70 percent of pre-disturbance vegetative density, which is a growing season and not a punch item. Seed in October in a northern climate and the Notice of Termination waits for spring green-up, and the GC won't close the site package or cut the last retention check until that NOT is filed.

WHAT TO DO

Three moves, in order

STEP 01
Track retention receivable by job with the expected stabilization date beside it, so cash forecasting runs off green-up dates and not off percent complete.
STEP 02
Seed inside the growing season when the schedule allows it, and when it doesn't, get temporary stabilization and the winter cost priced as its own line before you accept a fall seeding date.
STEP 03
Make the Notice of Termination a tracked closeout deliverable with one person on your side responsible for it, and bring retention aging to the monthly meeting the same way you bring AR.
QUESTIONS

What sitework owners ask

When does a site contractor get retainage released after final stabilization?

Your last retention check is stuck behind seed germinating in October, and germination depends on mother nature no matter when the work finished.

What does it cost?

The GC withholds 5 to 10 percent on work you performed 18 to 22 months earlier, and seeding season sets the release date. Bond and BMP maintenance cost keeps accruing the whole time.

What do I do first?

Track retention receivable by job with the expected stabilization date beside it, so cash forecasting runs off green-up dates and not off percent complete.

What are sitework contractors supposed to be making?

Sitework runs 18% gross margin, 15% overhead and 3% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade is 4 points below it. The CFOS target is 10%.

Which part of the system fixes it?

The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: The Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, andCONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for sitework contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, run by the same author.

What a fractional CFO does for sitework contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.