PAVING · CIVIL AND EARTHWORK · FIXED BY STEP 07

Base course in month two, retention released in month twenty

You place base and binder early so the site has something to drive on, then come back a year or two later for the surface. The bid priced one mobilization.

WHY IT'S A PAVING PROBLEM

Most subs finish their scope, punch out, and get released while the job is still moving. Paving is the trade whose scope is deliberately split across the entire schedule, so the money earned first is released last. The second trip also drags a full equipment package back to the site: paver, two rollers, a skid, a tack distributor, and lowboy moves, all charged against a single bid line that priced one mob.

WHAT IT COSTS

The size of it

5 to 10 percent of the first billing stays locked up for the life of the job, and the return trip runs $3,000 to $8,000 of unrecovered cost that never becomes a change order because it was never priced as a separate mobilization.

OVERHEAD AT $1M–$5M
14%
CFOS target 13% for paving.
GROSS MARGIN AT $1M–$5M
20%
CFOS target 23% for paving.
NET PROFIT AT $1M–$5M
6%
CFOS target 10% for paving.

Paving mobilises twice on a building job and usually gets paid for one. Aggregate base and the binder lift go down early so the site has a working surface, then you leave and come back for the wearing course and striping after the building is finished, because the surface lift can't survive construction traffic. On a mid-size commercial build those two trips fall 12 to 24 months apart. Retention on the month-two billing isn't released until final acceptance of the whole project, and the GC won't close you out early because paving is one of the last items on the punch list.

WHAT TO DO

Three moves, in order

STEP 01
Price the return trip as its own bid line with its own mobilization dollars, so the surface lift trip is sold rather than absorbed.
STEP 02
Track retainage by billing period on every job, so you can see which dollars came from the month-two invoice and how many months they have been outstanding.
STEP 03
Ask for early release of retention on completed base and binder work in writing the week you demobilize, while the GC still needs you to come back.
QUESTIONS

What paving owners ask

When do I get retainage released on base course paved two years ago?

You place base and binder early so the site has something to drive on, then come back a year or two later for the surface. The bid priced one mobilization.

What does it cost?

5 to 10 percent of the first billing stays locked up for the life of the job, and the return trip runs $3,000 to $8,000 of unrecovered cost that never becomes a change order because it was never priced as a separate mobilization.

What do I do first?

Price the return trip as its own bid line with its own mobilization dollars, so the surface lift trip is sold rather than absorbed.

What are paving contractors supposed to be making?

Paving runs 20% gross margin, 14% overhead and 6% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade is 1 point below it. The CFOS target is 10%.

Which part of the system fixes it?

The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: The Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for paving contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, run by the same author.

What a fractional CFO does for paving contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.