The half inch that goes uncaught until the plant statement posts
You sell square yards and you buy tons, so an overrun in the mat never reaches the pay app. It reaches the scale tickets, and most of those never get reconciled.
A drywall sub buys sheets and bills the same sheets, so an overrun shows at the supply house. Paving converts tons into square yards through a field setting a person on the machine adjusts. The paver operator, the GC, and the progress estimate can't see the conversion. So you track yield in job cost ticket by ticket. A monthly plant statement is far too late to be a control.
The size of it
On 10,000 square yards that eighth of an inch is roughly 69 extra tons. At $95 a ton that's about $6,500, on a job whose whole margin might be $30,000. One screed setting costs you three to four points of gross profit, and you find it 45 days later or not at all.
Yield overrun is the hardest margin loss in paving to catch. The unit you sell and the unit you buy are two different things, and they only meet on a scale ticket. Asphalt weighs about 110 pounds per square yard per inch, so a screed set an eighth of an inch heavy on a 2-inch mat overruns tonnage by 6.25 percent across the whole placement. Nothing looks wrong in the field. The mat looks right, and the billed square yards and the plan quantity both check out. Compaction, crown, and a soft base all push the same direction, so the loss adds up, and no line on the pay application ever shows it.
Three moves, in order
Step 01: Job cost structure
Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words.
What else costs paving contractors money
The same mechanism in other trades
What paving owners ask
Why does my asphalt tonnage come in over the estimate?
You sell square yards and you buy tons, so an overrun in the mat never reaches the pay app. It reaches the scale tickets, and most of those never get reconciled.
What does it cost?
On 10,000 square yards that eighth of an inch is roughly 69 extra tons. At $95 a ton that's about $6,500, on a job whose whole margin might be $30,000. One screed setting costs you three to four points of gross profit, and you find it 45 days later or not at all.
What do I do first?
Set a target tons per square yard for each mix and each lift during takeoff, and put that number on the crew's day sheet.
What are paving contractors supposed to be making?
Paving has 20% gross margin, 14% overhead and 6% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 1 point below it. The CFOS target is 10%.
Which part of the system fixes it?
The step is number 01, job cost structure. Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words. It comes from chapter 1 of CONTROL: C.F.O.S. Construction Financial Operating System.
Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for paving contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.
