Your elevator doesn't get built until layouts come back
Six weeks of architect and GC review stack on top of your lead time, not inside it, and the factory doesn't cut a rail until the stamped layout comes back.
Most subs measure lead time from the day they place the order. Yours starts the day an architect signs, which means the party holding your schedule has no money at risk in it. Two approvals, held by two different parties, come in front of a single manufacturing clock that can't start early.
The size of it
Six weeks of review plus a two-week out-of-tolerance hoistway fix moves the whole schedule two months to the right while you fund the deposit and burn estimated hours on a job with no billing activity.
Release for manufacture is gated on approved layout drawings: pit depth, overhead, hoistway plumb, entrance sizes, and machine room or MRL clearances. Until that approval comes back, the 20 to 40 week clock hasn't started, so every week the drawing waits on somebody's desk is a week added to the back end of the job. Then comes a second gate almost no other trade has, the field hoistway survey before mobilization. If the concrete or masonry is out of plumb or the pit runs short, you either eat rail bracket and entrance remediation or you stand down while another trade fixes structure. Both gates belong to other people, and both get blamed on the elevator sub.
Three moves, in order
Step 06: Project management
Billing dates, change orders, and notices, written as standards that work without anyone chasing them.
What else costs elevator contractors money
The same mechanism in other trades
What elevator owners ask
Elevator layout drawing approval took six weeks who pays for the delay?
Six weeks of architect and GC review stack on top of your lead time, not inside it, and the factory doesn't cut a rail until the stamped layout comes back.
What does it cost?
Six weeks of review plus a two-week out-of-tolerance hoistway fix moves the whole schedule two months to the right while you fund the deposit and burn estimated hours on a job with no billing activity.
What do I do first?
Date-stamp submittal out, approval in, and release to factory on every job, and age open submittals in your weekly meeting the same way you age AR.
What are elevator contractors supposed to be making?
Elevator runs 27% gross margin, 18% overhead and 9% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade is 2 points above it. The CFOS target is 12.5%.
Which part of the system fixes it?
The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone chasing them. It comes from chapter 6 of CONTROL: The Construction Financial Operating System.
Everything on this page is something you can install yourself, andCONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for elevator contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, run by the same author.
