Your elevator doesn't get built until layouts come back
Six weeks of architect and GC review get added on top of your lead time. The factory doesn't cut a rail until the stamped layout comes back.
Most subs measure lead time from the day they place the order. Yours starts the day an architect signs. The party holding your schedule has no money at risk in it. Two approvals, from two different parties, come before one manufacturing clock that can't start early.
The size of it
Six weeks of review plus a two-week fix on an out-of-tolerance hoistway moves the whole schedule two months later. Meanwhile you fund the deposit and spend estimated hours on a job with no billing activity.
Release for manufacture waits on approved layout drawings: pit depth, overhead, hoistway plumb, entrance sizes, and machine room or MRL clearances. Until approval comes back, the 20 to 40 week clock hasn't started. Every week the drawing waits on somebody's desk adds a week to the back end of the job. Then comes a second gate almost no other trade has, the field hoistway survey before mobilization. If the concrete or masonry is out of plumb or the pit is short, you pay for rail bracket and entrance fixes, or you stop work while another trade fixes structure. Both gates belong to other people, and the elevator sub gets the blame for both.
Three moves, in order
Step 06: Project management
Billing dates, change orders, and notices, written as standards that work without anyone following up on them.
What else costs elevator contractors money
The same mechanism in other trades
What elevator owners ask
Elevator layout drawing approval took six weeks who pays for the delay?
Six weeks of architect and GC review get added on top of your lead time. The factory doesn't cut a rail until the stamped layout comes back.
What does it cost?
Six weeks of review plus a two-week fix on an out-of-tolerance hoistway moves the whole schedule two months later. Meanwhile you fund the deposit and spend estimated hours on a job with no billing activity.
What do I do first?
Date-stamp submittal out, approval in, and release to factory on every job, and age open submittals in your weekly meeting the same way you age AR.
What are elevator contractors supposed to be making?
Elevator has 27% gross margin, 18% overhead and 9% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 2 points above it. The CFOS target is 12.5%.
Which part of the system fixes it?
The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It comes from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.
Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for elevator contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.
