CFOS for QuickBooks, coming January 2027See what you get
CARPENTRYCFOS-06
CARPENTRY · INTERIORS AND FINISHES · FIXED BY STEP 06

The cabinet clock doesn't start until someone signs

You won the job in March and the shop still hasn't cut a stick, because the shop drawings have not been stamped. The fabrication clock starts at approval, and the architect owns that date.

WHY IT'S A CARPENTRY PROBLEM

A plumber's long lead item is in a catalog, with a part number and a published lead time you can read before you bid. Yours doesn't exist yet. Your shop draws it. An architect with no deadline in your contract reviews it. Only then does anything get cut. So the biggest schedule risk on the job is a signature a purchase order can't speed up.

WHAT IT COSTS

The size of it

A crew sized for a start date that slides eight weeks either stays on your overhead or gets released and re-hired at a premium, and the shop slot you were holding gets sold to the next job. The span between award and first cash on a millwork package routinely lasts a full quarter with nothing to bill.

OVERHEAD AT $1M to $5M
13%
Derived from Framing, the nearest comparable trade. CFOS target 12%.
GROSS MARGIN AT $1M to $5M
18%
Derived from Framing, the nearest comparable trade. CFOS target 22%.
NET PROFIT AT $1M to $5M
5%
Derived from Framing, the nearest comparable trade. CFOS target 10%.

Custom millwork and casework take about 6 to 12 weeks of fabrication after shop drawing approval, and a complex package can reach 14 to 16 weeks. That's why the rule of thumb is drawings to the architect 12 to 16 weeks before install. Plated trusses and engineered floor systems have their own sequence: engineering and sealed drawings first, then permit, then two to six weeks of manufacturing. In both cases you produce the drawing, and someone else decides when it gets released.

WHAT TO DO

Three moves, in order

STEP 01
Put two dates on every millwork job in your job cost file: the award date and the stamped approval date. Build the labor plan off the second one.
STEP 02
Carve drafting, engineering, and submittal time into the schedule of values as its own line so those hours have somewhere to bill before any material ships.
STEP 03
Write the fabrication window into your agreement as a number of weeks from written approval, then send the GC a dated notice every week the stamp is still outstanding.
QUESTIONS

What carpentry owners ask

Why is my millwork taking 12 weeks after we already won the job?

You won the job in March and the shop still hasn't cut a stick, because the shop drawings have not been stamped. The fabrication clock starts at approval, and the architect owns that date.

What does it cost?

A crew sized for a start date that slides eight weeks either stays on your overhead or gets released and re-hired at a premium, and the shop slot you were holding gets sold to the next job. The span between award and first cash on a millwork package routinely lasts a full quarter with nothing to bill.

What do I do first?

Put two dates on every millwork job in your job cost file: the award date and the stamped approval date. Build the labor plan off the second one.

What are carpentry contractors supposed to be making?

No survey separates carpentry, so there is no figure of its own. The nearest comparable trade in the reference is Framing, which has 18% gross margin, 13% overhead and 5% net profit before taxes at $1M to $5M, with a CFOS target of 10% net. Those are derived figures, not carpentry's own. Read them as the neighbourhood, and read your own job costing as the answer.

Which part of the system fixes it?

The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It comes from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for carpentry contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What SPM The Construction CFO does, and what it costs

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.