CFOS for QuickBooks, coming January 2027See what you get
TELECOMCFOS-06
TELECOM · ELECTRICAL AND TECHNOLOGY · FIXED BY STEP 06

The Inspector's Signature Starts Your Pay Clock

Twelve thousand feet went in the ground in June and the invoice didn't move until September. The crews got paid in June.

WHY IT'S A TELECOM PROBLEM

Most trades bill a percent complete a GC can check on a walkthrough. Outside plant quantity gets accepted against a GIS deliverable: point files, stationing, sheet numbers and splice detail. An inspector who works for the carrier reviews it against a standards manual. A finished bore never gets taken on trust.

WHAT IT COSTS

The size of it

Sixty to ninety days of finished, cash-spent production stays in unbilled WIP behind paperwork, so you're financing crews and fuel on work that's done in the dirt and still unbillable.

OVERHEAD AT $1M to $5M
15%
CFOS target 14% for telecom.
GROSS MARGIN AT $1M to $5M
22%
CFOS target 24.5% for telecom.
NET PROFIT AT $1M to $5M
7%
CFOS target 10.5% for telecom.

The plow makes footage expensive. The as-built package makes it billable. Unit-price telecom pays per foot of bore, per foot of plow, per splice, per pole and per drop. The quantity isn't accepted until the carrier's inspector walks the footage package and signs it. Redlines come back over missing GPS points, wrong sheet numbers and splice diagrams. A field foreman with a phone camera was never equipped to produce those. So the paperwork sets your revenue and the crew sets your cost, and the two are two or three months apart.

WHAT TO DO

Three moves, in order

STEP 01
Make as-built acceptance its own milestone with an owner and a due date on the schedule, the same way a bore is.
STEP 02
Require the redline package for a segment before the crew leaves it: stationing, GPS points, sheet number, splice detail, and photos.
STEP 03
Report unbilled WIP by acceptance status every week so you can see how much cash is stuck behind documents.
QUESTIONS

What telecom owners ask

When can I invoice footage if the as builts aren't accepted yet?

Twelve thousand feet went in the ground in June and the invoice didn't move until September. The crews got paid in June.

What does it cost?

Sixty to ninety days of finished, cash-spent production stays in unbilled WIP behind paperwork, so you're financing crews and fuel on work that's done in the dirt and still unbillable.

What do I do first?

Make as-built acceptance its own milestone with an owner and a due date on the schedule, the same way a bore is.

What are telecom contractors supposed to be making?

Telecom has 22% gross margin, 15% overhead and 7% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.

Which part of the system fixes it?

The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It comes from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for telecom contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for telecom contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.