The Retention Waits On A Test Only You Can Pass

Retention releases against the commissioning agent's sign off, and the system being tested is yours. A building accepted in July can't prove its heating until the weather turns.

WHY IT'S A MECHANICAL PROBLEM

Drywall gets its retention when the walls are installed, finished, and inspected. Mechanical's release depends on a third party performance test on its own equipment. It's scheduled last, sometimes in the wrong season, and it waits on controls programming you may not even have the contract for. You're the first trade on the job and the last one paid, and the delay has nothing to do with the quality of your work.

WHAT IT COSTS

The size of it

Money earned in month two of a 20 month build releases in month 26 or later. At 10 percent retention on a $1.2M scope, that's $120K you finance for two full years. It's the same $120K that would have covered the next job's equipment deposit.

OVERHEAD AT $1M to $5M
16%
CFOS target 15% for mechanical.
GROSS MARGIN AT $1M to $5M
25%
CFOS target 27.5% for mechanical.
NET PROFIT AT $1M to $5M
9%
CFOS target 12.5% for mechanical.

Retention releases when functional performance testing passes, and that testing is on your equipment. You're on site from underslab and deck sleeves in month two. The money you earned then waits until the building is conditioned, the controls are programmed point to point, and TAB is complete. Then the opposite season clause applies. A building accepted in July can't have its heating sequences verified until fall, so final acceptance and the retention behind it wait 3 to 9 months past substantial completion. The other subs closed out long ago. You're still holding paper on work you finished eighteen months back.

WHAT TO DO

Three moves, in order

STEP 01
Track retention as its own receivable line per job on the WIP, spelling out the release event that governs it (TAB complete, FPT passed, and opposite season verification) with an expected date beside it.
STEP 02
Read the opposite season and commissioning clauses before signing, and negotiate partial release at TAB completion so the seasonal test doesn't hold the whole balance.
STEP 03
Request retention reduction at 50 percent completion in writing, attached to that month's pay app. Most contracts allow it and almost no contractor asks.
QUESTIONS

What mechanical owners ask

When does retention get released on a mechanical contract?

Retention releases against the commissioning agent's sign off, and the system being tested is yours. A building accepted in July can't prove its heating until the weather turns.

What does it cost?

Money earned in month two of a 20 month build releases in month 26 or later. At 10 percent retention on a $1.2M scope, that's $120K you finance for two full years. It's the same $120K that would have covered the next job's equipment deposit.

What do I do first?

Track retention as its own receivable line per job on the WIP, spelling out the release event that governs it (TAB complete, FPT passed, and opposite season verification) with an expected date beside it.

What are mechanical contractors supposed to be making?

Mechanical has 25% gross margin, 16% overhead and 9% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 2 points above it. The CFOS target is 12.5%.

Which part of the system fixes it?

The step is number 05, software and bookkeeping alignment. Live job costs inside thirty seconds, with the bookkeeping cadence that keeps them current. It comes from chapter 5 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for mechanical contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for mechanical contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.