The Retention Waits On A Test Only You Can Pass
Retention releases against the commissioning agent's sign off, and the system being tested is yours. A building accepted in July can't prove its heating until the weather turns.
Drywall gets its retention when the walls are hung, finished, and inspected. Mechanical's release event is a third party performance test on its own equipment, scheduled last, sometimes in the wrong season, and gated on controls programming you may not even hold the contract for. You're the first trade on the job and the last one paid, and the delay has nothing to do with the quality of your work.
The size of it
Money earned in month two of a 20 month build releases in month 26 or later. At 10 percent retention on a $1.2M scope that's $120K financed across two full years, and it's the same $120K that would have covered the next job's equipment deposit.
Retention releases when functional performance testing passes, and functional performance testing is your equipment. You're on site from underslab and deck sleeves in month two, but the money earned then rides until the building is conditioned, the controls are programmed point to point, and TAB is complete. Then the opposite season clause takes over: a building accepted in July can't have its heating sequences verified until fall, so final acceptance and the retention behind it defers 3 to 9 months past substantial completion. The other subs closed out long ago. You're still holding paper on work you finished eighteen months back.
Three moves, in order
Step 05: Software and bookkeeping alignment
Live job costs inside thirty seconds, with the bookkeeping cadence that keeps them true.
What else costs mechanical contractors money
The same mechanism in other trades
What mechanical owners ask
When does retention get released on a mechanical contract?
Retention releases against the commissioning agent's sign off, and the system being tested is yours. A building accepted in July can't prove its heating until the weather turns.
What does it cost?
Money earned in month two of a 20 month build releases in month 26 or later. At 10 percent retention on a $1.2M scope that's $120K financed across two full years, and it's the same $120K that would have covered the next job's equipment deposit.
What do I do first?
Carry retention as its own receivable line per job on the WIP, spelling out the release event that governs it (TAB complete, FPT passed, and opposite season verification) with an expected date beside it.
What are mechanical contractors supposed to be making?
Mechanical runs 25% gross margin, 16% overhead and 9% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 2 points above it. The CFOS target is 11%.
Which part of the system fixes it?
The step is number 05, software and bookkeeping alignment. Live job costs inside thirty seconds, with the bookkeeping cadence that keeps them true. It comes from chapter 5 of CONTROL: The Construction Financial Operating System.
