Fab Release Is Gated By Two Clocks You Don't Own
The coil line has nothing to cut because the engineer has held your submittals for five weeks and the coordination model is still bouncing. You pay shop payroll either way.
The sprinkler contractor draws around your duct, and the drywall contractor doesn't have a fab shop on payroll waiting for an engineer's stamp. Mechanical is the only trade that models first for everyone else and pays fixed weekly shop labor while approvals wait. Other parties cause both delays, and both end up in your P&L. The shop costs you money every week of it.
The size of it
Five weeks of review stacks on top of a 30 week equipment lead time, and none of it shows in job cost. It turns up as shop underabsorption and a missed rough-in date the GC files as your delay.
Nothing gets cut in the shop until coordination drawings are signed and submittals come back approved, and you don't control either clock. Duct is the largest object in the ceiling, so BIM coordination routes mechanical first. You pay the modeling cost up front and absorb every re-route when electrical, sprinkler, and plumbing come back at you. The equipment and sheet metal submittals wait on the engineer's desk. The spec says 14 days, and you get 4 to 6 weeks. Fabrication release waits on that approval, and the coil line costs the same every week whether there's a released package to cut or an empty rack.
Three moves, in order
Step 06: Project management
Billing dates, change orders, and notices, written as standards that work without anyone following up on them.
What else costs mechanical contractors money
The same mechanism in other trades
What mechanical owners ask
Engineer has had my mechanical submittals for five weeks?
The coil line has nothing to cut because the engineer has held your submittals for five weeks and the coordination model is still bouncing. You pay shop payroll either way.
What does it cost?
Five weeks of review stacks on top of a 30 week equipment lead time, and none of it shows in job cost. It turns up as shop underabsorption and a missed rough-in date the GC files as your delay.
What do I do first?
Keep a submittal log with the date sent, the contract review days, and the date each package came back, and attach it to every pay app so the record exists before the schedule dispute.
What are mechanical contractors supposed to be making?
Mechanical has 25% gross margin, 16% overhead and 9% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 2 points above it. The CFOS target is 12.5%.
Which part of the system fixes it?
The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It comes from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.
Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for mechanical contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.
