CFOS for QuickBooks, coming January 2027See what you get
MECHANICALCFOS-06
MECHANICAL · MECHANICAL AND LIFE SAFETY · FIXED BY STEP 06

Nine Trips To The Job, Two Of Them Billable

Your crew makes nine separate trips to that building, from underslab to punch. The schedule of values has one line on it that says rough-in.

WHY IT'S A MECHANICAL PROBLEM

A drywall crew comes in, installs board, finishes, and leaves. Mechanical work is in every phase from the slab to the ceiling grid, so the schedule keeps calling you back. Your equipment also serves as the building's temporary heat while other trades finish. The schedule creates both costs, the return trips and the temp use, and neither one has an SOV line.

WHAT IT COSTS

The size of it

You absorb four to six unbudgeted mobilizations at $3K to $6K each on a mid-size job, plus temp-use wear with no change order. That's $25K to $40K of cost with no billing line.

OVERHEAD AT $1M to $5M
16%
CFOS target 15% for mechanical.
GROSS MARGIN AT $1M to $5M
25%
CFOS target 27.5% for mechanical.
NET PROFIT AT $1M to $5M
9%
CFOS target 12.5% for mechanical.

The trips are underslab, deck sleeves and hangers, overhead rough-in, roof curbs before the roofer dries in, unit sets on a crane day the GC picks, ceiling trim after the drywall, start-up, TAB, and punch. That's eight or nine separate visits, each with its own travel, lift rental, and foreman ramp-up time. The schedule of values bills by system percentage, so remobilization cost never reaches a billing line. Then the GC asks to operate the permanent equipment for temporary heat during drywall. You pay for construction filters, coil cleaning, and belt wear on units the owner hasn't accepted. The warranty clock on that equipment starts months before the owner takes the building.

WHAT TO DO

Three moves, in order

STEP 01
Write the full mobilization list into the SOV at buyout and put a dollar value on each one: underslab, sleeves and hangers, overhead rough, roof curbs, unit sets, trim, start-up, TAB, and punch.
STEP 02
Open a cost code per mobilization so travel, lift rental, and foreman ramp post where they really occur, and you can price the next job off history.
STEP 03
Send a temporary heat letter before the GC turns a unit on: construction filters, coil cleaning, belt replacement, and warranty start date at owner acceptance, priced as a change order and signed before startup.
QUESTIONS

What mechanical owners ask

How to bill for multiple mobilizations on a mechanical job?

Your crew makes nine separate trips to that building, from underslab to punch. The schedule of values has one line on it that says rough-in.

What does it cost?

You absorb four to six unbudgeted mobilizations at $3K to $6K each on a mid-size job, plus temp-use wear with no change order. That's $25K to $40K of cost with no billing line.

What do I do first?

Write the full mobilization list into the SOV at buyout and put a dollar value on each one: underslab, sleeves and hangers, overhead rough, roof curbs, unit sets, trim, start-up, TAB, and punch.

What are mechanical contractors supposed to be making?

Mechanical has 25% gross margin, 16% overhead and 9% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 2 points above it. The CFOS target is 12.5%.

Which part of the system fixes it?

The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It comes from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for mechanical contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for mechanical contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.