Nine Trips To The Job, Two Of Them Billable
Your crew makes nine separate trips to that building, from underslab to punch. The schedule of values has one line on it that says rough-in.
A drywall crew comes in, installs board, finishes, and leaves. Mechanical work is in every phase from the slab to the ceiling grid, so the schedule keeps calling you back. Your equipment also serves as the building's temporary heat while other trades finish. The schedule creates both costs, the return trips and the temp use, and neither one has an SOV line.
The size of it
You absorb four to six unbudgeted mobilizations at $3K to $6K each on a mid-size job, plus temp-use wear with no change order. That's $25K to $40K of cost with no billing line.
The trips are underslab, deck sleeves and hangers, overhead rough-in, roof curbs before the roofer dries in, unit sets on a crane day the GC picks, ceiling trim after the drywall, start-up, TAB, and punch. That's eight or nine separate visits, each with its own travel, lift rental, and foreman ramp-up time. The schedule of values bills by system percentage, so remobilization cost never reaches a billing line. Then the GC asks to operate the permanent equipment for temporary heat during drywall. You pay for construction filters, coil cleaning, and belt wear on units the owner hasn't accepted. The warranty clock on that equipment starts months before the owner takes the building.
Three moves, in order
Step 06: Project management
Billing dates, change orders, and notices, written as standards that work without anyone following up on them.
What else costs mechanical contractors money
The same mechanism in other trades
What mechanical owners ask
How to bill for multiple mobilizations on a mechanical job?
Your crew makes nine separate trips to that building, from underslab to punch. The schedule of values has one line on it that says rough-in.
What does it cost?
You absorb four to six unbudgeted mobilizations at $3K to $6K each on a mid-size job, plus temp-use wear with no change order. That's $25K to $40K of cost with no billing line.
What do I do first?
Write the full mobilization list into the SOV at buyout and put a dollar value on each one: underslab, sleeves and hangers, overhead rough, roof curbs, unit sets, trim, start-up, TAB, and punch.
What are mechanical contractors supposed to be making?
Mechanical has 25% gross margin, 16% overhead and 9% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 2 points above it. The CFOS target is 12.5%.
Which part of the system fixes it?
The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It comes from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.
Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for mechanical contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.
