CFOS for QuickBooks, coming January 2027See what you get
LANDSCAPINGCFOS-01
LANDSCAPING · LANDSCAPE AND IRRIGATION · FIXED BY STEP 01

Sleeving goes in month two and bills like nothing

Fifteen percent of your material goes under the pavement early and bills as three percent of a pay application, because the whole scope is billed on one schedule of values line.

WHY IT'S A LANDSCAPING PROBLEM

A trade that installs once, in order, can work with one percent-complete line because its cost is spread evenly. Your cost is front-loaded with underground pipe that can't be inspected. Then it repeats four more times across eighteen months. Percent complete on one line assumes a straight burn, and irrigation cost doesn't follow one.

WHAT IT COSTS

The size of it

Four unbudgeted mobilizations get absorbed as if they were overhead, and the job shows a bid margin no crew in your company can reach.

OVERHEAD AT $1M to $5M
15%
CFOS target 14% for landscaping.
GROSS MARGIN AT $1M to $5M
22%
CFOS target 24.5% for landscaping.
NET PROFIT AT $1M to $5M
7%
CFOS target 10.5% for landscaping.

Irrigation is four to six separate trips across the whole job calendar. Sleeving goes in at subgrade before curb and paving. Mainline and POC follow wet utilities. Laterals and heads follow finish grade and go in before sod. Startup and coverage testing come due at substantial completion. Punch and adjust happen after every other trade is gone. Each trip is a truck, a crew, a trencher on a trailer, and travel time. The GC's schedule of values usually has one line called irrigation. So early underground material bills as a sliver of the whole, and every return trip bills as zero.

WHAT TO DO

Three moves, in order

STEP 01
Send the GC a five line irrigation breakdown before the first pay application: sleeving, mainline and POC, laterals and heads, startup and testing, and punch.
STEP 02
Give every mobilization its own cost code with labor, truck, and equipment hours attached, and total them at closeout.
STEP 03
Add a stored and installed materials line so sleeve pipe placed at subgrade converts to cash without waiting on the coverage test.
QUESTIONS

What landscaping owners ask

How to bill irrigation sleeving installed months before the rest?

Fifteen percent of your material goes under the pavement early and bills as three percent of a pay application, because the whole scope is billed on one schedule of values line.

What does it cost?

Four unbudgeted mobilizations get absorbed as if they were overhead, and the job shows a bid margin no crew in your company can reach.

What do I do first?

Send the GC a five line irrigation breakdown before the first pay application: sleeving, mainline and POC, laterals and heads, startup and testing, and punch.

What are landscaping contractors supposed to be making?

Landscaping has 22% gross margin, 15% overhead and 7% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.

Which part of the system fixes it?

The step is number 01, job cost structure. Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words. It comes from chapter 1 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for landscaping contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for landscaping contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.