A Density Tech's Calendar Controls Your Fill Schedule
The next lift doesn't go down until the lab comes out and shoots it. That lab answers to the owner's geotech.
This trade sells compacted volume, and it isn't finished until an outsider certifies it. A stranger decides tomorrow's production. No install-and-leave trade has that problem. Your daily limit gets set on a calendar you don't control, and iron and crew wait until somebody else's technician comes through the gate.
The size of it
Two half days a week waiting on a density tech across a 12 week fill operation is roughly 12 lost machine days. At $8,000 to $20,000 a day of direct idle cost for a mid-size fleet, that's $96,000 to $240,000 absorbed inside a job that just looks like it underperformed.
A third party you don't hire and can't schedule sets the pace of a fill operation. Every lift has to reach its compaction spec, commonly 95% of standard Proctor verified with a nuclear gauge, before the next lift goes on. The tech with that gauge works for the owner's geotech firm on the owner's calendar. Subgrade acceptance works the same way, through a proof roll the geotech signs. Fail it and you undercut and replace right away, then argue about the change order once the owner's engineer prices it. Your fleet uses fuel and payroll the whole time. No cost code says waiting on the lab, so the delay never reads as a delay, and the job just comes in soft.
Three moves, in order
Step 06: Project management
Billing dates, change orders, and notices, written as standards that work without anyone following up on them.
What else costs grading contractors money
The same mechanism in other trades
What grading owners ask
Who pays when my crew waits on compaction testing?
The next lift doesn't go down until the lab comes out and shoots it. That lab answers to the owner's geotech.
What does it cost?
Two half days a week waiting on a density tech across a 12 week fill operation is roughly 12 lost machine days. At $8,000 to $20,000 a day of direct idle cost for a mid-size fleet, that's $96,000 to $240,000 absorbed inside a job that just looks like it underperformed.
What do I do first?
Open a standby cost code on every job with fill and make foremen code idle hours to it in half day increments, with the cause written on the ticket.
What are grading contractors supposed to be making?
Grading has 18% gross margin, 16% overhead and 2% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 5 points below it. The CFOS target is 10%.
Which part of the system fixes it?
The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It comes from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.
Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for grading contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.
