Five Trips To Site, One Mobilization Line Item
Clearing, mass grade, trench backfill, subgrade, and final grade are five separate visits spread across the GC's whole schedule, and you bid them as one number.
A trade that comes to the site once brings a van and stays until the work is done. This trade drags a fleet on trailers back to the same site five times, at another company's convenience, against a mobilization budget funded in month one. Returning costs more here than it does for anyone else on the job, and it's the cost most often bid as a single event.
The size of it
Five machines moved four extra times at $600 to $1,200 per lowboy leg is $24K to $48K of unbid transport on one job. It charges to a mobilization code that emptied itself before the second trip.
A grading contract is four to seven distinct site operations, and lump sum sitework prices a single mobilization. Clearing and grubbing, mass grade, utility trench backfill, building pads, subgrade under paving, and final grade with topsoil and stabilization each fall at a different point in the general contractor's schedule. Every one of them is a lowboy leg per machine in and back out for the dozer, excavator, roller, water truck, and skid steer, plus a crew day to reset survey and grade control. Trips three through seven have no money behind them. The spacing belongs to the GC, so you can't batch the work to save the moves either.
Three moves, in order
Step 01: Job cost structure
Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words.
What else costs grading contractors money
The same mechanism in other trades
What grading owners ask
How do i price remobilization on a sitework bid?
Clearing, mass grade, trench backfill, subgrade, and final grade are five separate visits spread across the GC's whole schedule, and you bid them as one number.
What does it cost?
Five machines moved four extra times at $600 to $1,200 per lowboy leg is $24K to $48K of unbid transport on one job. It charges to a mobilization code that emptied itself before the second trip.
What do I do first?
Split the mobilization cost code into one numbered code per site visit, so the third and fourth trips have somewhere real to post.
What are grading contractors supposed to be making?
Grading runs 18% gross margin, 16% overhead and 2% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 5 points below it. The CFOS target is 10%.
Which part of the system fixes it?
The step is number 01, job cost structure. Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words. It comes from chapter 1 of CONTROL: The Construction Financial Operating System.
