GRADING · CIVIL AND EARTHWORK · FIXED BY STEP 07

Earned In Month Two, Retention Paid In Month Twenty-Two

Mass grading is finished before the foundation is poured, and the retention on it sits until somebody else's building reaches substantial completion.

WHY IT IS A GRADING PROBLEM

Retention is timed to the end of a schedule, and this trade's work sits at the very front of it. A trade finishing near closeout waits weeks for release, while a grading sub waits the entire length of the vertical build. Finishing early is what makes the wait long. You get punished for the one thing the GC asked you to do first.

WHAT IT COSTS

The size of it

On a $1.2M sitework contract at 10%, that's $120K out of the business for roughly twenty months while you fund the next mobilization on a line of credit. That's a full crew's annual payroll parked on somebody else's balance sheet.

OVERHEAD AT $1M–$5M
16%
CFOS target 15% for grading.
GROSS MARGIN AT $1M–$5M
18%
CFOS target 25% for grading.
NET PROFIT AT $1M–$5M
2%
CFOS target 10% for grading.

Grading earns most of its contract value in the first ninety days of a two year build, then waits on every trade behind it to release the last ten percent. Mass grade is commonly 60% to 75% of a sitework contract, and it's complete before the first footing goes in. Retention of 5% to 10% is withheld against the general contractor's substantial completion date, which has nothing to do with the day your work was accepted. No trade on the job starts earlier, so no trade waits longer between earning money and collecting it. Pay when paid stretches the progress billings on top of that, which pushes your working capital need well past the retention itself.

WHAT TO DO

Three moves, in order

STEP 01
Build one schedule of every open retention balance by job, with the GC's projected substantial completion date beside each one, and update it monthly.
STEP 02
Negotiate stepped release at a percentage of your own completed value into the next sitework subcontract before you sign it, and be willing to trade price for it.
STEP 03
Charge the interest on your line of credit to overhead on purpose, so the cost of financing other people's schedules stops hiding inside the P&L.
QUESTIONS

What grading owners ask

When do i get retention on a sitework contract?

Mass grading is finished before the foundation is poured, and the retention on it sits until somebody else's building reaches substantial completion.

What does it cost?

On a $1.2M sitework contract at 10%, that's $120K out of the business for roughly twenty months while you fund the next mobilization on a line of credit. That's a full crew's annual payroll parked on somebody else's balance sheet.

What do I do first?

Build one schedule of every open retention balance by job, with the GC's projected substantial completion date beside each one, and update it monthly.

What are grading contractors supposed to be making?

Grading runs 18% gross margin, 16% overhead and 2% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 5 points below it. The CFOS target is 10%.

Which part of the system fixes it?

The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: The Construction Financial Operating System.

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Josh Luebker ran commercial construction projects before he ran the numbers behind them, on data centres, military bases, hospitals, and high-rises. He wrote CONTROL: The Construction Financial Operating System, which is an eight-step framework for commercial subcontractors, and it publishes on October 1, 2026. He is a master electrician who moved into the office and kept the field vocabulary.

Sulphur Prairie Operations LLC maintains the benchmark reference behind these figures. Every edition is reconciled against the newest CFMA survey release before it publishes here. Where a figure changes between editions, the older edition keeps its year in the title so a citation to it stays correct.

Eight steps. Sixty days.

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It publishes on October 1, 2026. Eight steps, six working templates, and the order they install in.