First trade in, last one paid, and held twice
The pad has been finished and traveled on for two years and the GC is still holding ten percent of your contract.
Every other subcontractor's retention clock starts near the end of the job, with substantial completion in sight. Yours starts at the beginning and lasts the whole length of a building you never touched. Weather and seed germination set the end, and pushing can't speed them up. Your direct costs, the fuel, the trucking, the imported fill and the payroll, all cleared your bank account before the steel went up.
The size of it
On a $1.2M sitework contract that's $60K to $120K held out 20 to 26 months, financed on your line of credit. You paid for the work that earned it out of pocket in the first 90 days.
Mass grading and underground are usually done inside the first 10% to 20% of an 18 to 30 month build. Retainage of 5% to 10% releases at substantial completion of the whole project. Then it waits another 30, 60 or 90 days for the GC to collect and pass it down. Sitework has a second gate no other trade has. The GC often won't release site retention until the stormwater permit is terminated. Final stabilization means 70% of pre-construction perennial vegetative cover, and grass is seasonal. Miss the growing window and the Notice of Termination waits for next spring, and so does your retainage. In arid regions the permit allows up to three years of vegetation establishment.
Three moves, in order
Step 07: Monthly cadence
Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month.
What else costs excavation contractors money
The same mechanism in other trades
What excavation owners ask
How long does site retainage take to be released on sitework?
The pad has been finished and traveled on for two years and the GC is still holding ten percent of your contract.
What does it cost?
On a $1.2M sitework contract that's $60K to $120K held out 20 to 26 months, financed on your line of credit. You paid for the work that earned it out of pocket in the first 90 days.
What do I do first?
Age retention by job on its own monthly schedule, with the substantial completion date and the seeding window written next to each balance.
What are excavation contractors supposed to be making?
Excavation has 21% gross margin, 14% overhead and 7% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.
Which part of the system fixes it?
The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: C.F.O.S. Construction Financial Operating System.
Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for excavation contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.
