The manhole is late and the trench is still open
The pipe is laid, the hole is dug, and the whole job stops because a manhole barrel and a frame and grate are still weeks out at the plant.
A vertical trade stores its material dry in a conex and waits for the call. Excavation can't pause like that. The trench is already open, so shoring boxes, trench plates, dewatering pumps, traffic control, and a backfill crew on standby cost money every day. None of it is a pay item on the schedule of values. Base doesn't go down until the underground is in and tested. One late casting sets the paving date, and the paving date comes back at you as a delay claim.
The size of it
Open trench costs reach the thousands a day in rented shoring, pumps, plates, and idle crew, with no line to bill against. Then the delay turns into paving liquidated damages you never priced.
Precast drainage structures, box culverts, frames and grates, and pipe specials like bends, tees, hydrants, and valves get built to your plan sheet. Lead times are commonly 8 to 16 weeks. Even commodity ductile iron is stock to 6 weeks after receipt of order per McWane, and specials take longer. You find out the morning the crew reaches the structure location and there's nothing to set. From then on the trench stays open and the rental clock keeps adding up. The storm and sanitary system is the hold point for base and paving, so the delay reaches the GC's schedule too.
Three moves, in order
Step 06: Project management
Billing dates, change orders, and notices, written as standards that work without anyone following up on them.
What else costs excavation contractors money
The same mechanism in other trades
What excavation owners ask
How do I charge for waiting on precast structures to be delivered?
The pipe is laid, the hole is dug, and the whole job stops because a manhole barrel and a frame and grate are still weeks out at the plant.
What does it cost?
Open trench costs reach the thousands a day in rented shoring, pumps, plates, and idle crew, with no line to bill against. Then the delay turns into paving liquidated damages you never priced.
What do I do first?
Pull every precast structure, casting, and pipe special off the plans the week you're awarded, and get submittals to the supplier before a machine moves.
What are excavation contractors supposed to be making?
Excavation has 21% gross margin, 14% overhead and 7% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.
Which part of the system fixes it?
The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It comes from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.
Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for excavation contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.
