EXCAVATION · CIVIL AND EARTHWORK · FIXED BY STEP 06

The manhole is late and the trench is still open

The pipe is laid, the hole is dug, and the whole run stops because a manhole barrel and a frame and grate are still weeks out at the plant.

WHY IT'S AN EXCAVATION PROBLEM

A vertical trade stages its material dry in a conex and waits for the call. Excavation has no such pause: the run is already open, so shoring boxes, trench plates, dewatering pumps, traffic control, and a backfill crew on standby keep accruing every single day, and none of it is a pay item on the schedule of values. Base doesn't go down until the underground is in and tested, so one late casting becomes the paving date, and the paving date comes back at you as a delay claim.

WHAT IT COSTS

The size of it

Open-trench cost runs into the thousands a day in rented shoring, pumps, plates, and idle crew, with no line to bill it against. Then the schedule hit turns into paving liquidated damages you never priced.

OVERHEAD AT $1M–$5M
14%
CFOS target 13% for excavation.
GROSS MARGIN AT $1M–$5M
21%
CFOS target 23.5% for excavation.
NET PROFIT AT $1M–$5M
7%
CFOS target 10.5% for excavation.

Precast drainage structures, box culverts, frames and grates, and pipe specials like bends, tees, hydrants, and valves get built to your plan sheet, not pulled off a shelf. Lead times commonly run 8 to 16 weeks, and even commodity ductile iron runs stock to 6 weeks after receipt of order per McWane, with specials longer. Most owners find out the hard way, on the morning the crew reaches the structure location and there's nothing to set. From that morning forward the trench stays open, the rental clock keeps running, and the storm and sanitary system is the hold point for base and paving, so the slip hits the GC's schedule too.

WHAT TO DO

Three moves, in order

STEP 01
Pull every precast structure, casting, and pipe special off the plans the week you're awarded, and get submittals to the supplier before a machine moves.
STEP 02
Put a dated release and delivery column beside each structure in the job file, so the shipping date is right next to the money.
STEP 03
Code shoring, plates, pumps, and traffic control separately from production, so standby days become a number you can give the GC in writing.
QUESTIONS

What excavation owners ask

How do I charge for waiting on precast structures to be delivered?

The pipe is laid, the hole is dug, and the whole run stops because a manhole barrel and a frame and grate are still weeks out at the plant.

What does it cost?

Open-trench cost runs into the thousands a day in rented shoring, pumps, plates, and idle crew, with no line to bill it against. Then the schedule hit turns into paving liquidated damages you never priced.

What do I do first?

Pull every precast structure, casting, and pipe special off the plans the week you're awarded, and get submittals to the supplier before a machine moves.

What are excavation contractors supposed to be making?

Excavation runs 21% gross margin, 14% overhead and 7% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.

Which part of the system fixes it?

The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone chasing them. It comes from chapter 6 of CONTROL: The Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, andCONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for excavation contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, run by the same author.

What a fractional CFO does for excavation contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.