Failed density stops the job and starts an argument
The geotech red-tagged the proof roll, the fix is two feet of undercut and select fill, and no one on the GC's side is writing a ticket for it.
Excavation is the one scope where a third party you didn't hire decides when you can cover your work. Once it's covered, no one can see the evidence. The quantity in dispute is thousands of yards moving at machine speed while the argument is still open. Every hour you wait for written direction is idle iron. Every hour you keep digging without it is money you may never get back.
The size of it
Undercut and select fill costs $25 to $45 a yard placed with haul. A 2-foot undercut across a 3-acre pad is roughly 10,000 yards. That's a six-figure difference. Cover it before the change order is written and it can turn a 12% job into a loss.
Nothing gets covered and no next lift goes down until the proof roll and nuclear density tests pass spec, typically 95% Standard Proctor. The lab works for the owner or the GC, on their schedule, so your production waits while somebody else decides if you passed. When it fails, the spec language decides who pays. If it calls the material unsuitable, undercut and select fill import is extra work. If it calls it moisture conditioning or contractor means and methods, you disc, dry, re-roll, and re-test on your own nickel. The geotech report you bid from is usually furnished for information only under a disclaimer clause. Unclassified excavation language makes rock and soft soil yours no matter what the borings showed.
Three moves, in order
Step 01: Job cost structure
Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words.
What else costs excavation contractors money
The same mechanism in other trades
What excavation owners ask
Is undercut extra work or included in unclassified excavation?
The geotech red-tagged the proof roll, the fix is two feet of undercut and select fill, and no one on the GC's side is writing a ticket for it.
What does it cost?
Undercut and select fill costs $25 to $45 a yard placed with haul. A 2-foot undercut across a 3-acre pad is roughly 10,000 yards. That's a six-figure difference. Cover it before the change order is written and it can turn a 12% job into a loss.
What do I do first?
Read the earthwork spec for the words unsuitable, unclassified, and moisture conditioning before you bid, and write exclusions against the ones that move the risk to you.
What are excavation contractors supposed to be making?
Excavation has 21% gross margin, 14% overhead and 7% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.
Which part of the system fixes it?
The step is number 01, job cost structure. Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words. It comes from chapter 1 of CONTROL: C.F.O.S. Construction Financial Operating System.
Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for excavation contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.
