THE MATH

Overbilled, and still behind in cash

The WIP schedule says you billed 6, 8 and 10 percent more than the work you've done. Then 45 days pass before the money is paid. This page does the math on what that wait costs you.

Published October 17, 2026. Updated October 17, 2026.

THE ANSWER

With 45 day payment terms, an overbilling of 6, 8 or 10 percent of contract value leaves any job shorter than 15 months behind the work done in cash.

On a $1,000,000 job that lasts 6 months, 45 days of unpaid billing is $250,000, or 25.00 percent of the contract. An overbilling of 10 percent is $100,000. Cash is $150,000 behind the work done, even though the WIP schedule reads overbilled.

  • Overbilling. Overbilling is the amount billed above the work done: billings in excess of earned revenue. This page states it as a percent of contract value.
  • Receivable. The receivable is the billing you have sent and not yet collected. With an even billing pace it equals the last payment term of billing.
  • Model. The model bills and earns evenly across the job, uses 30 day months, and counts the receivable as the last payment term of billing. Cash against the work done is the overbilling minus the receivable.
BY JOB LENGTH

Cash against the work done at 45 day terms

A $1,000,000 contract. Each cell is the dollars ahead of or behind the work done once the first payment cycle has passed, for an overbilling of 6, 8 and 10 percent of contract value.

Cash against the work done by job length and overbilling, at 45 day payment terms. Updated October 17, 2026.
Job lengthUnpaid billing6% overbilled8% overbilled10% overbilled
3 months$500,000 (50.00%)$440,000 behind$420,000 behind$400,000 behind
6 months$250,000 (25.00%)$190,000 behind$170,000 behind$150,000 behind
9 months$166,700 (16.67%)$106,700 behind$86,700 behind$66,700 behind
12 months$125,000 (12.50%)$65,000 behind$45,000 behind$25,000 behind
18 months$83,300 (8.33%)$23,300 behind$3,300 behind$16,700 ahead
24 months$62,500 (6.25%)$2,500 behind$17,500 ahead$37,500 ahead
THE BREAK EVEN

How long a job has to be before the overbilling covers the wait

15 months. Overbilling covers the receivable only when the overbilling rate times the job length reaches the payment term in months, so 10 percent needs a job of 15 months or longer, and 6 percent needs 25 months, 8 percent needs 18.8 months and 10 percent needs 15 months at 45 day terms.

Job length in months at which overbilling covers the payment term, by payment terms and overbilling. Updated October 17, 2026.
Payment terms6% overbilled8% overbilled10% overbilled
30 days16.7 months12.5 months10 months
45 days25 months18.8 months15 months
60 days33.3 months25 months20 months
75 days41.7 months31.3 months25 months
90 days50 months37.5 months30 months
WHAT THE INDUSTRY REPORTS

Research from another source

These figures come from another company's survey, not from Run On CFOS. Each one cites the report and the page.

Billd's 2026 National Subcontractor Market Report found subcontractors reported waiting an average of 51 days for payment, against 35 days reported by general contractors.

Source: Billd, 2026 National Subcontractor Market Report, pages 4 and 5 (survey of 623 respondents, published May 13, 2026).

The report doesn't state when the 51 days start. The 2024 and 2025 reports measured the wait from the pay application.

Billd's 2026 National Subcontractor Market Report found 79 percent of subcontractors use supplier terms to buy materials, and 77 percent have supplier terms of 45 days or less.

Source: Billd, 2026 National Subcontractor Market Report, page 9 (survey of 623 respondents, published May 13, 2026).

The report's text says 77 percent and its chart for the same question reads 78 percent.

Billd's National Subcontractor Market Reports put the average subcontractor payment wait at 57 days in 2024, 56 days in 2025 and 51 days in 2026.

Source: Billd, 2024 National Subcontractor Market Report, page 4 (survey of 696 respondents, published April 22, 2024); Billd, 2025 National Subcontractor Market Report, page 3 (survey of over 800 construction professionals, published April 15, 2025); Billd, 2026 National Subcontractor Market Report, page 4 (survey of 623 respondents, published May 13, 2026).

The 2024 and 2025 reports measured the wait from the pay application. The 2026 report doesn't state a starting point, so read the three figures as a direction and not as a like for like trend.

HOW TO READ IT

What this does and doesn't say

Overbilled is a billing number
The WIP schedule compares billings to earned revenue. It doesn't count the money still owed to you, so a schedule that reads overbilled can appear next to a bank balance that's behind the work.
The wait is the receivable
Each day of payment terms is a day of billing you have sent and not collected. Forty five days is a month and a half of billing, and on a short job that's a large share of the contract.
Where the model stops
Retainage isn't in these numbers. Every dollar of retainage held back adds to the receivable, so it makes the result worse. A pay app front loaded with mobilization or material can bill more than the even pace, and that's the one way a short job covers its payment term.

To see the same wait in your own numbers, the 13 week cash flow forecast puts each pay app on the day the money is paid. Related reading: pay when paid and the cash it costs you and underbilling that hides a loss.

THE DATA

Download the math

Every job length, every payment term and every overbilling rate in the model, as a spreadsheet and as JSON. Both include the date and the credit on every row, and both change when this page changes.

QUESTIONS

What readers ask

What does overbilled mean in construction?

Overbilling is the amount billed above the work done: billings in excess of earned revenue. This page states it as a percent of contract value.

Why am I short on cash when my WIP schedule says I'm overbilled?

On a $1,000,000 job that lasts 6 months, 45 days of unpaid billing is $250,000, or 25.00 percent of the contract. An overbilling of 10 percent is $100,000. Cash is $150,000 behind the work done, even though the WIP schedule reads overbilled.

How long does a job have to be before a 10 percent overbilling covers 45 days of waiting?

15 months. Overbilling covers the receivable only when the overbilling rate times the job length reaches the payment term in months, so 10 percent needs a job of 15 months or longer, and 6 percent needs 25 months, 8 percent needs 18.8 months and 10 percent needs 15 months at 45 day terms.

Does retainage change this?

Yes. Retainage that's held back adds to what you're owed and haven't collected, so the cash position is worse than the table shows.

CITING

If you are quoting this page

CITE THIS

Run On CFOS. Overbilling against payment terms. 2026. Sulphur Prairie Operations, LLC. https://runoncfos.com/overbilling-and-45-day-terms. CC BY 4.0.

Figures on this page were last revised 2026-10-17. Published under CC BY 4.0, which permits reuse of any figure here, including commercially, as long as the credit above travels with it. The same figures in machine-readable form: /overbilling-and-45-day-terms.json.

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.