SOLAR · ELECTRICAL AND TECHNOLOGY · FIXED BY STEP 07

Your retention is released by a document reviewer

The physical work ended months ago. What's still holding your last 5 to 10 percent is a commissioning binder and a stack of payroll records.

WHY IT'S A SOLAR PROBLEM

Other trades get held for punch work, and punch work is fixable with a truck and a Tuesday. A solar sub gets held because a tax equity reviewer three parties removed needs to prove the array performs and the labor was paid correctly, and neither of those is something a foreman can go fix. The retention is functionally collateral on somebody else's tax credit.

WHAT IT COSTS

The size of it

Five to ten percent of contract value ages six to twelve months past the last day of physical work, gated by a reviewer you've never met. A $5M solar sub has $250k to $500k tied up inside closeout binders and payroll files.

OVERHEAD AT $1M–$5M
15%
CFOS target 14% for solar.
GROSS MARGIN AT $1M–$5M
22%
CFOS target 24.5% for solar.
NET PROFIT AT $1M–$5M
7%
CFOS target 10.5% for solar.

Solar works late in the build, but the holdback runs past the last day of labor and turns into a paperwork exercise. The release list is a commissioning report, IV curve traces, a thermal scan, as-builts, O&M manuals, warranty registrations, and monitoring portal credentials turned over to the owner. On ITC jobs it goes further, because the owner's 30 percent credit and the 5x multiplier depend on the sub's prevailing wage and registered apprenticeship records, so owners hold retainage and indemnity against certified payroll most solar shops were never set up to produce. DOL exposure for a miss is $5,000 per worker per year plus back wages with interest, and $50 per labor hour on apprenticeship shortfalls, $500 if the miss is intentional. Residential works the same way at smaller scale: two or three crew-days of physical work stretched across a 90 to 120 day contract-to-PTO cash cycle.

WHAT TO DO

Three moves, in order

STEP 01
Take the owner's closeout list, turn it into a cost-coded task with an assigned owner and a due date, and schedule it at the 80 percent completion point, not after energization.
STEP 02
Set certified payroll and apprenticeship hour tracking up on day one of any ITC job, because these records can't be reconstructed later.
STEP 03
Run an aged retention report every month with the specific missing document listed next to each dollar amount, and work the top three in your monthly meeting.
QUESTIONS

What solar owners ask

Why is my solar retainage still held after commissioning?

The physical work ended months ago. What's still holding your last 5 to 10 percent is a commissioning binder and a stack of payroll records.

What does it cost?

Five to ten percent of contract value ages six to twelve months past the last day of physical work, gated by a reviewer you've never met. A $5M solar sub has $250k to $500k tied up inside closeout binders and payroll files.

What do I do first?

Take the owner's closeout list, turn it into a cost-coded task with an assigned owner and a due date, and schedule it at the 80 percent completion point, not after energization.

What are solar contractors supposed to be making?

Solar runs 22% gross margin, 15% overhead and 7% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.

Which part of the system fixes it?

The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: The Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, andCONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for solar contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, run by the same author.

What a fractional CFO does for solar contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.