CFOS for QuickBooks, coming January 2027See what you get
PLUMBINGCFOS-07
PLUMBING · MECHANICAL AND LIFE SAFETY · FIXED BY STEP 07

You Earn It in Month Two and Collect in Month Twenty-Six

You were in the dirt before the steel got there, and you'll see that retention when the building opens.

WHY IT'S A PLUMBING PROBLEM

Plumbing goes in the ground first and trims out last. No other trade on the job is at both ends. A site contractor bills early and closes out early. A finish trade bills late, then waits a short time for release. Plumbing bills at the front of a two year schedule and collects at the back of it. So retention on your earliest and most exposed work is held the longest, and it funds somebody else's project the whole time.

WHAT IT COSTS

The size of it

Retention held on a plumbing contract often exceeds the whole profit on that job for most of the job's life. You earned that margin in month two. You collect it in month twenty-six, and you finance it the whole way.

OVERHEAD AT $1M to $5M
16%
CFOS target 15% for plumbing.
GROSS MARGIN AT $1M to $5M
25%
CFOS target 27.5% for plumbing.
NET PROFIT AT $1M to $5M
9%
CFOS target 12.5% for plumbing.

Plumbing is usually the first sub billing on a building after sitework and one of the last to finish. So retention gets held on the earliest money and released on the latest date. Underground and underslab go in before the slab. The slab comes before steel, and steel comes before everything else. Retention of 5 to 10 percent comes off every progress payment and doesn't release until final completion of the whole building, 18 to 24 months later. You can't claim early substantial completion the way a site trade can, because your crew comes back for trim and final test. The last 10 to 15 percent of contract value is that trim. It waits on drywall, paint, and tile. So you stay at 85 to 90 percent billed for months, with the balance and every dollar of retention still out.

WHAT TO DO

Three moves, in order

STEP 01
Put retention receivable on its own line by job and read it every month next to the profit on that same job, so what you're financing becomes a number and stops being a feeling.
STEP 02
Ask for retention reduction at 50 percent completion and a separate release for the underground scope at slab. Do it during subcontract review, while you can still negotiate.
STEP 03
Review every job stuck between 85 and 95 percent billed in the monthly meeting, and follow up on the trim release with the superintendent in writing, with a date on it, before it turns into another quarter.
QUESTIONS

What plumbing owners ask

Why is plumbing retention held so long on commercial jobs?

You were in the dirt before the steel got there, and you'll see that retention when the building opens.

What does it cost?

Retention held on a plumbing contract often exceeds the whole profit on that job for most of the job's life. You earned that margin in month two. You collect it in month twenty-six, and you finance it the whole way.

What do I do first?

Put retention receivable on its own line by job and read it every month next to the profit on that same job, so what you're financing becomes a number and stops being a feeling.

What are plumbing contractors supposed to be making?

Plumbing has 25% gross margin, 16% overhead and 9% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is 2 points above it. The CFOS target is 12.5%.

Which part of the system fixes it?

The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for plumbing contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for plumbing contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.