Two approval clocks stand between you and the factory
Nothing releases to the factory until the hardware schedule submittal comes back and the keying conference happens. Neither clock starts when you sign.
Both clocks belong to the design team and the owner, and neither starts the day you get the contract. A finish trade that buys stock material never needs an architect's stamp plus an owner's keying decision before anything can ship. Five weeks with the architect and an unscheduled keying conference compress your buyout window to whatever is left, while the price you signed keeps aging.
The size of it
Every week the submittal sits is a week closer to the next manufacturer increase, and on a hard bid you cover that difference yourself.
No published benchmark reference breaks this trade out on its own. CFMA reports at NAICS level, and at that level this trade rolls into a broader bucket with several others. That's why this page carries mechanisms and no margin figures. It reports inside NAICS 238350 Finish Carpentry, so there's no door and hardware margin figure to put in this box. The 48 trades that do publish average 7% net profit at $1M–$5M before taxes, which is the nearest reference point worth anything here.
Two other people have to finish their part before your material moves. The hardware schedule submittal has to come back approved or approved-as-noted, and a rejected item resubmits and restarts the clock from the top. The second clock is the keying conference, where the owner, the distributor, and the locksmith build the master key hierarchy, and no cylinder or core can be ordered until that meeting happens. Master key system design alone runs $1,500 to $25,000 depending on project size, and the meeting gets scheduled around the building owner's calendar.
Three moves, in order
Step 06: Project management
Billing dates, change orders, and notices, run as standards that hold without anyone chasing them.
What else costs door and hardware contractors money
The same mechanism in other trades
What door and hardware owners ask
Hardware submittal approved but keying conference not scheduled?
Nothing releases to the factory until the hardware schedule submittal comes back and the keying conference happens. Neither clock starts when you sign.
What does it cost?
Every week the submittal sits is a week closer to the next manufacturer increase, and on a hard bid you cover that difference yourself.
What do I do first?
Log the transmittal date and the contract's stated review period on the same line, and send a one-sentence status ask every Friday until it comes back.
Are there published benchmarks for door and hardware?
No, and this site won't print one. No published benchmark reference breaks this trade out on its own. CFMA reports at NAICS level, and at that level this trade rolls into a broader bucket with several others. That's why this page carries mechanisms and no margin figures. In the surveys it rolls into NAICS 238350 Finish Carpentry, so the closest honest reference is the 48-trade table, where net profit at $1M–$5M averages 7% before taxes. Read that as the neighbourhood, and read your own job costing as the answer.
Which part of the system fixes it?
The step is number 06, project management. Billing dates, change orders, and notices, run as standards that hold without anyone chasing them. It comes from chapter 6 of CONTROL: The Construction Financial Operating System.
